Caqabadaha mashruucca dhismaha maktabaddu lakulmay iyo kuwa wali taagan.
==============////////=====////////============
Caqabadda koowaad ee sababtay jiitanka bilowga mashruuccan waxay ahayd helitaanka dhul laga dhiso maktabadda oo adkaaday.
10ki July 2019 waxaa lagu wareejiyay guddiga dhismaha maktabadda xarunta dhalinyarada MMG muddo yar kabacdina waxaa soo baxday inay macquul ahayn in dhismuhu noqdo xaruntaas sababo badan oo jiray awgeed waxaana mar labaad loo badalay schoolka mashkooke iyadoo hawlwadeennada lawareegeen warqadda caddaynta 12 ka August 2020 halka siwada jir ah loo dhagax dhigay schoolka mashkooke 18 August 2020.
Waxaa lagu dhisay bakhaarki dhismaha goobti ladhagax dhigay 21 April 2021 iyadoo loo diyaar garoobay bilowga shaqada dhismaha.
Wuxuu mar saddexaad hakad kuyimid bilowgii dhismaha sabab laxidhiidha dhulka oo la go'aamiyay in loo badalo mar saddexaad garoonka weerar iyadoo si rasmiya dhismuhu ubilowday 21 Nov 2022.
Iyadoo Muddo kudhow Afar sano ay shaqadu utaagnayd sabab dhul laxidhiidha wali dhulka dhismaha laga bilaabay lama hayyo sharcigiisi waxayna arrinkaas hor istaagtay dadaallo muddo lawaday oo taageero lagaga heli lahaa deeq bixiyaal danaynayay kaqayb qaadashada mashruucan.
Caqabadaha kalee dhulka ka baxsan post ga xiga............