Lowdham Flood Storage Reservoir

Lowdham Flood Storage Reservoir The village of Lowdham has suffered a long history of devastating flooding, including two major flood events in the winter of 2023/2024.

This page will provide regular updates on the construction progress of the EA Flood Storage Reservoir in Lowdham.

02/06/2026

Latest update from the construction site.

12/05/2026

Following the winter, 2026 earthworks are well underway.

17/03/2026

Our planned five month winter break ends on Monday 13 April, when our contractor will bring excavators and equipment back to site and activity will resume for the 2026 earthworks season.

On Lambley Road, temporary traffic lights will be in place from 30 March for around four weeks while we reinstate and seed the road verges.

04/12/2025

Nottinghamshire County Council's drone footage of a wet reservoir construction site. Following a successful 2025 earthworks season where we constructed everything as planned, site activities will now pause until the spring. This is in accordance with our programme.

07/11/2025

Check out a quick clip of the latest drone footage of the construction site - courtesy of Nottinghamshire County Council

01/10/2025

To prevent water seeping through the ground beneath the reservoir embankment, we are installing a bentonite cut off trench along the full length. The bentonite is mixed with cement, installed as a slurry which then sets..

23/09/2025

Join us for the latest tour of the construction site.

22/09/2025

The work on Lambley Road continues, you'll have seen the road and verge improvements over recent months. We have permission to extend the temporary traffic lights to the end of October to allow us to complete this work. If we can remove these temporary traffic lights before the end of October, we will.

13/08/2025

Making the most of the good weather: reservoir taking shape to the left now covering the concrete flow control structure. Works upstream and downstream of the structure are almost complete. Great progress by our contractor Jackson Civil Engineering, thanks to Nottinghamshire County Council for the drone footage.

05/08/2025

The work on Lambley Road continues, the road will now remain open on temporary traffic lights while our contractor Jacksons finish the road verge and reinstate hedging. This will continue into September to allow us to complete everything required.

Address

Lowdham

Alerts

Be the first to know and let us send you an email when Lowdham Flood Storage Reservoir posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organisation

Send a message to Lowdham Flood Storage Reservoir:

Share