23/06/2026
Marlow Bridge update on major restoration works
I was delighted to welcome the new Buckinghamshire Council Chief Executive Zina Etheridge , and Deputy Leader Thomas Broom , for a site visit of Marlow Bridge to show them your Conservative Council delivering for our residents.
Works included :
• South Abutment ( where the bridge joins to the river bank ) complete, North Abutment & South Pier underway
• All 12 new bearings ( see pictures) delivered and fully tested.
• Second stage of lighting on the bridge is booked for 13th July 2026.
Weekday closures from 8 pm to 6 pm over the next four weeks :
• 22nd - 23rd June
• 26th,27th,28th June
• 4th - 5th July
• 13th,14th,15th,16th July
Closures will allow 1 footway for pedestrians to be open throughout .
Next update in early August
Phase 1 targeted for completion by the end of September.
Phase 2 will start during 2027.