04/09/2025
This substantial education infrastructure, nearing significant completion, cannot be abandoned to the mercies of the weather and to the disadvantage of students and the people of Upper Denkyira West. The projects, awarded in December 2019, are at various stages of completion as follows:
1. Boys Dormitory- 74%,
2. Girls Dormitory- 50%,
3. Administration block- 98%,
4. Assembly Hall- 85%,
5. Dining Hall with kitchen- 89%,
6. 3-storey teachers' flat- 85%,
7. Headmaster's bungalow- 91%,
8. Assistant Headmaster's bungalow- 91%.
Given the government's investment of over GHS32m in these projects, and the clarion call by Ghanaians for prudent spending of state resources, it is imperative that government makes the remaining additional commitments to fully complete these projects.
I humbly call on the President, the Minister of Education, and the GETFund administrator to as a matter of importance release funds to WINGET and re-award the terminated SARBET contract to get these critical projects completed for my beloved Upper Denkyira West constituency. .