EDU Infrastructure Programme

EDU Infrastructure Programme Building a Brighter Future Together.

MEYR is investing €91M over 13 years to modernise schools with integrated technology, flexible and eco- friendly design and improved indoor and outdoor facilities for the wellbeing of students, educators, and staff.

Pieta Primary School - Works in ProgressComprehensive refurbishment of corridors, the hall, classrooms, and associated a...
05/09/2026

Pieta Primary School - Works in Progress

Comprehensive refurbishment of corridors, the hall, classrooms, and associated areas, aimed at improving the overall condition, functionality, comfort, and quality of the building. These interventions are intended to create a safer, more comfortable, and more welcoming educational environment, better suited to the needs of students and staff and more conducive to effective teaching and learning.

Paola Primary - Works in ProgressRefurbishment and upgrading works for the new toilet and bathroom facilities, including...
29/08/2026

Paola Primary - Works in Progress

Refurbishment and upgrading works for the new toilet and bathroom facilities, including accessible facilities for persons with disabilities, are currently in progress. The works include the installation of new sanitary fittings, plumbing and drainage systems, electrical and lighting installations, wall and floor finishes, ventilation systems, accessibility features, and all associated fixtures and fittings.

29/08/2026

L-Iskola Primarja tal-Belt Valletta, li tifforma parti mill-Kulleġġ San Ġorġ Preca, għaddejja minn tiġdid estensiv…

Blata l-Bajda Middle School - Renovation of internal blocks and external recreational areas- Works in ProgressComprehens...
27/08/2026

Blata l-Bajda Middle School - Renovation of internal blocks and external recreational areas- Works in Progress

Comprehensive renovation works are being carried out to the courtyard, classrooms, and adjoining spaces, including the removal of deteriorated paint finishes, the repair and preparation of walls and other surfaces, and the upgrading of internal finishes. The project also includes the installation of new electrical systems, distribution boards, lighting and power infrastructure, plumbing, sanitary and drainage systems, as well as air conditioning and photovoltaic installations. In addition, associated building services are being upgraded and coordinated, while remedial works to internal areas and the application of new waterproofing systems to roof surfaces are also being undertaken.

These interventions are aimed at enhancing safety, functionality, durability, energy efficiency, and the overall quality of the learning environment, while preserving and respecting the school's existing architectural character

Mosta Secondary (Lily of the Valley) - Works in ProgressOngoing works are being carried out on the school roofs and on t...
22/08/2026

Mosta Secondary (Lily of the Valley) - Works in Progress

Ongoing works are being carried out on the school roofs and on the external and internal façades. These interventions include repair, refurbishment and finishing works aimed at improving the structural condition, weather protection, appearance and overall functionality of the school buildings.

Mrieħel Secondary School – Works in ProgressThe library renovation project is nearing completion.Renovation works on the...
21/08/2026

Mrieħel Secondary School – Works in Progress

The library renovation project is nearing completion.

Renovation works on the school hall are also underway and include the installation of insulated wall systems, air-conditioning and a ventilation system. The project also involves the construction of a new stage and internal structures within the hall, as well as the refurbishment of the façade.

Xogħol avvanzat ta’ rinnovazzjoni u tisbieħ bħala parti mill-Edu Infrastructure Programme, ġewwa l-Iskola Primarja Ave M...
28/05/2026

Xogħol avvanzat ta’ rinnovazzjoni u tisbieħ bħala parti mill-Edu Infrastructure Programme, ġewwa l-Iskola Primarja Ave Maria Xgħajra, fi ħdan il-Kulleġġ Santa Margerita. Dan il-proġett jinkludi l-bini mill-ġdid tal-ħajt perimetrali tal-iskola kif ukoll interventi ta’ tisbieħ u titjieb fil-faċilitajiet sportivi għall-benefiċċju tal-istudenti.

Xogħol ta’ rinnovazzjoni u tisbieħ ġewwa l-iskola primarja Ave Maria Xgħajra, fi ħdan il-Kulleġġ Santa Margerita, fejn q...
04/05/2026

Xogħol ta’ rinnovazzjoni u tisbieħ ġewwa l-iskola primarja Ave Maria Xgħajra, fi ħdan il-Kulleġġ Santa Margerita, fejn qiegħed jinbena mill-ġdid il-ħajt tal-madwar tal-iskola kif ukoll tisbieħ tal-faċilitajiet sportivi għall-istudenti.

Xogħol ta’ restawr u tisbieħ ġewwa l-btieħi tal-Iskola Primarja Ġużè Ebejer, Dingli, fi ħdan il-kulleġġ San Nikola, fejn...
30/04/2026

Xogħol ta’ restawr u tisbieħ ġewwa l-btieħi tal-Iskola Primarja Ġużè Ebejer, Dingli, fi ħdan il-kulleġġ San Nikola, fejn qed isir xogħol ta’ titjieb tal-faċilitajiet sportivi għall-istudenti.

L-ewwel fażi tar-rinnovazzjoni tal-iskola Alternative Learning Programme (ALP), fi ħdan il-Kulleġġ San Tumas More Paola,...
27/04/2026

L-ewwel fażi tar-rinnovazzjoni tal-iskola Alternative Learning Programme (ALP), fi ħdan il-Kulleġġ San Tumas More Paola, ġiet konkluża b’suċċess. Is-sala ġiet mgħammra b’sistema ta’ arja kkundizzjonata, kif ukoll b’sistemi tad-dawl u tas-sound tal-ogħla livell. Saret ukoll manutenzjoni estensiva fuq il-faċċata, l-ispazji esterni u l-bitħa prinċipali tal-iskola. Dan il-proġett twettaq b’investiment li jaqbeż il miljun ewro.

Address

Ministry For Education, Sport, Youth, Research And Innovation (MEYR) Great Siege Road
Il-Furjana
VLT2000

Alerts

Be the first to know and let us send you an email when EDU Infrastructure Programme posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share

Category