06/09/2026
In view of the current Grid Status, and as advised by the System Operator, the National Grid Corporation of the Philippines (NGCP), MECO ๐ข๐๐ฎ ๐๐ constrained to implement ๐ ๐ฎ๐ป๐๐ฎ๐น ๐๐ผ๐ฎ๐ฑ ๐๐ฟ๐ผ๐ฝ๐ฝ๐ถ๐ป๐ด (๐ ๐๐) on all areas ๐๐ช๐ ๐ฉ๐ค ๐๐ฃ๐จ๐ช๐๐๐๐๐๐๐ฃ๐ฉ ๐๐ง๐๐ ๐ฅ๐ค๐ฌ๐๐ง ๐จ๐ช๐ฅ๐ฅ๐ก๐ฎ.
The following Feeders might be interrupted on ๐๐๐ฉ๐ญ๐๐ฆ๐๐๐ซ ๐, ๐๐๐๐ (๐๐ฎ๐ง๐๐๐ฒ) until alert advisories will be lifted by NGCP:
โผ๏ธ๐๐ฅ๐๐๐ฌ๐ ๐ง๐จ๐ญ๐ ๐ญ๐ก๐๐ญ ๐ญ๐ก๐๐ฌ๐ ๐ฌ๐๐ก๐๐๐ฎ๐ฅ๐๐ฌ ๐๐ซ๐ ๐ญ๐๐ง๐ญ๐๐ญ๐ข๐ฏ๐ ๐๐ง๐ ๐ฆ๐๐ฒ ๐๐ ๐๐ก๐๐ง๐ ๐๐ ๐ฐ๐ข๐ญ๐ก๐จ๐ฎ๐ญ ๐ฉ๐ซ๐ข๐จ๐ซ ๐ง๐จ๐ญ๐ข๐๐ ๐๐๐ฉ๐๐ง๐๐ข๐ง๐ ๐จ๐ง ๐ญ๐ก๐ ๐๐ข๐ซ๐๐๐ญ๐ข๐ฏ๐ ๐๐ง๐ ๐๐๐ฏ๐ข๐ฌ๐จ๐ซ๐ฒ ๐๐ซ๐จ๐ฆ ๐๐๐๐ โผ๏ธ
๐
๐ซ๐จ๐ฆ ๐:๐๐๐๐ ๐ญ๐จ ๐:๐๐๐๐ ๐๐จ๐ซ ๐ ๐ฆ๐๐ฑ๐ข๐ฆ๐ฎ๐ฆ ๐๐ฎ๐ซ๐๐ญ๐ข๐จ๐ง ๐จ๐ ๐จ๐ง๐ (๐) ๐ก๐จ๐ฎ๐ซ ๐ฉ๐๐ซ ๐๐๐๐๐๐ซ
Feeder 1 โ
Feeder 1A โ
Feeder 3 โ
Feeder 4 โ
Feeder 7โ
Feeder 8 โ
Feeder 11 โ
Feeder 12 โ
Feeder 13 โ
Feeder 17 โ
Feeder 18-
We sincerely apologize for the inconvenience this situation may cause. We wish to reiterate that it is not the desire of MECO for our consumers to experience inconvenience brought by the power interruption as this is beyond MECOโs control.
We thank our consumers for their patience and understanding.
Junard "Ahong" Chan
Mayor Cindi King Chan
VISAYAS GRID ALERT STATUS
Update as of 6 September 2026, 8AM
Yellow Alert
6:00PM- 9:00PM
Available Capacity - 2,405MW
Peak Demand - 2,295MW
9 plants are on forced outage on September, 6 plants are on forced outage since August 2026, 1 plant since July, 2 plants since June, 7 plants since May, 3 plants since 2025, 2 plants since 2024, 2 plants since 2023, and 1 plant since 2021, while 15 plants are running on derated capacities, for a total of 877.5MW unavailable to the grid.
Factor/s that contributed to the YELLOW Alert declaration:
1. Unavailability of Visayas' large coal plants TVI 1 and PEDC 3
2. Deration of PCPC
3. Limited power import from Mindanao
A yellow alert is issued when the operating margin is insufficient to meet the transmission gridโs contingency requirement.