11/18/2019
Good Morning Everyone,
This week in construction:
Landscapers will finish working on planting and irrigation between Yucca and Madrone St. They have begun working in Phase 4 between Madrone St. and Juniper Wy.
Electrical (streetlight poles and conduit) will be finishing in Phase 3 between Yucca Street and Madrone, and starting in Phase 4 as noted above.
New driveways, curb & gutter, and sidewalk will be installed in Phase 3 in the locations noted above.
Our crews will be working on the Northeast quadrant of the Buchanan Blvd. and Boulder City Pkwy. intersection beginning this Sunday evening, and open said quadrant Tuesday morning back to traffic. Electrical improvements will also be performed at the intersection during this time.
We have begun working Phase 4 of the project, which is between Bullock Dr. and Juniper Wy. on South side of Boulder City Pkwy.
We also would like to make you aware of sections of the street that will not have streetlights as we remove old lights and construct new foundations and new light poles. We apologize for the inconvenience and ask that you be safe during these times.
PLEASE NOTE....if you only have one driveway, we will be reaching out personally to discuss how to construct it with you. If you have two driveways, one driveway will always stay open.