09/01/2026
** update at the bottom**
A few questions have arisen regarding the roundabout status at Hwy 213 and Q. All work on this intersection was stopped on July 31st due to Spectrum. They were notified a year ago about the upcoming construction but never moved their fiber lines in the area out of the construction zone. Up until August 25th, they have not bothered to reply to any e-mail or phone calls to provide a schedule to complete their move. They finally responded and met onsite this morning to stake out the route for the new lines. This will delay project completion to approximately December 18th. They hope to start the move on Thursday and will take about 2 weeks to complete.
Milling and Paving is expected to start on September 28th through October 9th on one lane from the roundabout to Hwy 11, once done they will complete the other lane in the same manner.
The railroad will be reconstructing the crossing at S. Center St and Beloit St. Project is scheduled to start October 5th and expected to take about a week to complete.
West Beloit St. curb and gutter is substantially completed. This work will continue on East Beloit St.
As always, schedule is tentative due to unforeseen circumstances that may arise.
UPDATE:
There are several good questions in the comments, so here are a few clarifications.
STH 213 is a State project. The Village participates in regular project meetings, including a meeting scheduled for Tuesday, but the Village does not control the State’s construction process, contractor requirements, utility relocation process, or any fines or penalties that may apply.
We do know that Spectrum was contacted multiple times regarding the necessary utility relocation. The Village does not have enough information to answer questions about whether Spectrum can or will be fined, charged for delays, or held responsible for business losses, and we do not want to speculate.
STH 213 remains closed to through traffic. Local access is still permitted for residents, businesses, visitors, and others who have a destination within the construction area. Using STH 213 simply as a route through Orfordville to reach a destination outside the Village is not considered local access.
Access to individual side roads may change as construction progresses, so drivers should continue to follow posted barricades and construction signage.
For specific questions regarding construction scheduling, access, or the State project itself, the project manager is:
Tim Sina, P.E.
Strand Associates, Inc.
608-217-6333
[email protected]
The Village will continue sharing updates as information is provided through the project team.