12/06/2026
Major works are underway at the Bayview and Brinsmead reservoirs to strengthen water storage capacity ahead of the next wet season.
The reservoirs were taken offline in mid-2024 for maintenance and refurbishment which uncovered deterioration to the roofs that requires full replacements.
Contractors are now onsite at the Bayview and Brinsmead reservoirs, undertaking the $24 million project to remove and replace the roofs on both structures and complete relining prior to recommissioning.
These images show: Part of the Bayview reservoir roof being removed and replaced with a lighter, more durable metal structure designed to extend the life of this critical infrastructure.