02/09/2026
🚧 Works Update - 2 September 2026 🚧
Kyogle Memorial Recreation Centre is really starting to take shape, with the roof on the sports hall expected to be completed by the end of the week.
All structural steelwork has now been finished and most of the internal framing is in place. The contractor is continuing with external cladding works while progressing internal fit-out activities, including electrical installation.
Once completed, the centre will feature ceiling-mounted basketball hoops, netball facilities, indoor soccer goal posts, and line marking for a range of sports. The facility will also include a multi-purpose meeting space with a kitchenette, a parents' room, and public amenities. The hall will be available for community and sporting event hire and will also serve as an evacuation centre during emergencies, providing an important community asset for the region.
The rainfall experienced in the middle of last week caused minor delays to the approach works at Montgomerys Bridge, with the concrete approach slabs completed later than originally scheduled. This week, the crew is undertaking site clean-up and completing the remaining approach works. Pavement construction and bitumen sealing are programmed for completion on Friday.
Clarkes Lane Bridge – preparation works are underway for the concrete deck pour scheduled for mid-week. Once the deck pour is complete, abutment backfilling and approach earthworks are planned for later in the week.
Reconstruction works on Gardner Lane have recommenced, with kerb and gutter construction now underway.
Ongoing flood damage repairs:
🔹Gradys Creek Road: Stabilising and sealing works completed, tidying up works continue
🔹Edenville Road Rehab: Works starting this week with shoulder cleaning
🔹Iron Pot Creek Road: Council continues to monitor the landslip daily
🔹Horseshoe Creek Road: Works progressing
🔹Baileys Bridge Road: Sheet piling in progress
🔹Gradys Creek Road landslip: Works progressing
🔹Richmond River Landslip: Benching works and rock placement in progress on number 1 slip
🔹Williams Road Landslip: Works progressing
Grading crews are continuing work across the region, currently undertaking grading on Creegans Road in the Cawongla catchment and Murray Scrub Road in the Afterlee catchment.
The Bonalbo crew is working on Dyraaba Road and will then move into the Deep Creek catchment. Maintenance activities are also continuing, with a pipe replacement underway on Bingeebeebra Road at Mummulgum.
Highway maintenance activities include slashing along the entire length of Summerland Way, while on the Bruxner Highway at Mallanganee Range crews are continuing with pavement widening, slope maintenance and drainage improvement works.
Photo: The Kyogle Memorial Recreation Centre is progressing