19/06/2026
As part of the 14km Coffs Harbour Bypass - one of Australia's largest infrastructure projects - Borger Cranes contributed to over twenty bridge and major lift operations along the route.
At Roberts Hill, the brief was precise: install two technical modules, each nearly 20 metres long and weighing up to 47.2 tonnes, onto elevated steel posts - with fixing tolerances measured in millimetres.
The LIEBHERR LTM1500 was rigged overnight. Eight lift points. A test-lift. Then the real thing - twice, back to back, on a schedule that allowed no downtime between placements.
Precision isn't just a word for us. On jobs like this, it's the only way the work gets done.
π Roberts Hill | Coffs Harbour Bypass, NSW
ποΈ LIEBHERR LTM1500 | 45.3t + 47.2t