The Rural Municipality Taché Community Centre project is steadily coming along with several subtrades on site.
Cast In Place Concrete have been working on slab prep for the activity center, and have poured all the changeroom slabs, along with the Ice resurfacing room slab, and the mechanical room slab.
Diamond Excavating's crew have been working on slab prep grading and are currently working on the arena slab prep.
Ambrosie Electrical is continuing to work on the rough ins for the electrical, including the changerooms, and the changeroom washrooms.
Penn Lite's Plumbing crew have been working on the changeroom washroom rough-ins including the showers, and the underground plumbing in the arena and activity center. Penn Lite's HVAC crew have continued to work on the HVAC layout in various locations on site.
Prairie HVAC's crew have been working on the arena brine lines for the ice rink and have moved the ice plant skid into the mech room.
Avalon Drywall's crew have been erecting the steel stud walls in various areas on site, including the second floor from the top of the masonry walls on the mezzanine to the underside of the ceiling.
Simmons masonry has been erecting masonry walls in the changerooms, changeroom washrooms, second floor mezzanine, and second floor washrooms.
Normandeau Roofing's crew have been plugging away at the library roof, the activity center roof, and the arena shed roof (Back of the building).
Claude Simard Metal Systems crew have been placing their exterior rigid insulation, and associated channels. They have started the corrugated siding on the East side of the Library this week.