Some updated information from Stirling Council regarding the closure of the A81 this week:
“Good Afternoon,
Stirling Council intend to undertake essential carriageway resurfacing works on the A81 Glasgow Road, Blanefield commencing on Thursday 20th of August for a period of 4 days, excluding weekends with all works being completed on Tuesday 25th of August (weather permitting). This timescale has been reviewed in consultation with the contractor to reduce disruption and the impact on the community as far as reasonably practicable.
The works involve the excavation of the existing carriageway, laying the new binder course, resetting any ironwork, laying the new surface course and reinstating the traffic islands.
This section of carriageway was prioritised using our risk-based inspection matrix following site inspections, reported defects, complaints and increased insurance claims due to the poor condition.
Unfortunately, it is not possible to undertake these works without a full road closure as we require a safe working zone keeping our workforce and road users free from any hazard or risk whilst the absolute minimum a vehicle running lane can be is 3m which is not achievable on this site meaning temporary traffic signals would not be appropriate.
It is also not possible to undertake the works overnight due to the many residential properties in the area and restrictions on noise during the works period.
Notification of the works has been done by resident letters; advance warning signs and all road works can be found here: Scottish Road Works Online
We apologise for any inconvenience these works may cause; however, we aim to keep this as minimal as possible and complete the works in a timely manner.
Regards,
Alistair Schofield, Team Leader - Roads Maintenance”