22/05/2026
INFORMATION FROM CADENT
Drop-in session to be held on the 26th May 9:00-12:00 next to the Community Centre and the Vine Lounge
Cadent are investing in upgrading gas network in the village, replacing ageing metal pipes with more durable plastic pipes. This will increase the resilience of the network and make reactive repairs and disruption less likely in the future.
As part of this programme, they will be replacing parts of the network in and around Thorney Road, Capel St Mary, Ipswich. Starting 26 May 2026 until approximately 13th September 2026.
To minimise disruption to the community, they will be consulting with residents, businesses and stakeholders in the area whilst planning the project in collaboration with Suffolk highways authority officers.
Traffic management: They will be setting up temporary traffic lights on most junctions to manage the flow of traffic in order to ensure safety of the team and the public.
Before work starts:
• Advanced Warning Signage (AWS)
• Bespoke letter detailing the purpose of the works, traffic management, website link and details of the drop-in session
• Drop-in session held on the 26th May 9:00-12:00 next to the Community Centre and the Vine Lounge, for residents and businesses to attend and ask any questions
• Social media posts on Next Door & Facebook
• Letter notification for customers with gas interruptions
• Customer Care Officer visit to customers with gas interruptions
• SMS & Email notification to customers with gas interruptions
During works:
• Site signage with varying messages
After works:
• Customer Care Officer visit to customers with gas interruptions