13/08/2026
Work is continuing to move forward at both our new crematorium developments in Cramlington and Vale of York.
At Great North Crematorium & Memorial Gardens, the chapel roof is now fully boarded and ready for membranes, while work continues on the gable end. Electrical works are progressing inside the chapel, alongside window installation and further works to the cremator room, where ceiling boarding is nearing completion.
At Vale of York Crematorium & Memorial Gardens, block paving and external works are progressing, while first-fix electrical and mechanical works continue internally. The cremator room is also taking shape, with high-level painting complete and ceiling boarding underway.
It’s great to see both projects continuing to progress, with each development moving closer to completion. We look forward to sharing further updates as work continues.