We have received an update regarding the ongoing ground stabilisation works on Forest Road, Lydney.
Following recent ground surveys, additional areas of instability were identified within the project area. To prevent future disruption and avoid having to reopen the site later, the decision has been made to complete all required stabilisation works under a single, coordinated programme.
The project is now anticipated to be completed in Summer 2027 (subject to ground conditions and ongoing progress).
Undertaking all necessary works now ensures long-term ground stability for Forest Road and avoids repeated road closures in the future.
For full details, project updates, and FAQs regarding the extended schedule, please visit the official project page here: https://www.gloucestershire.gov.uk/major-projects-list/geotechnical-and-structural/forest-road-lydney/