11/09/2026
NDR MAINTENANCE WORKS-NIGHT CLOSURES.
Information from Norfolk County Council Highways.
I thought it would be prudent to make you aware of some planned large scale works we will be carrying out along the NDR over several weeks. These works will be to carry out verge scalping & vegetation cutting, gully cleansing, w**d spraying, kerb works, graffiti removal & sign replacement which will involve several agencies working together.
It is intended that the work will be completed under a road closure between three sections between 20:00 and 05:00 Mon – Fri. This will ensure minimal disruption to the public and businesses.
• The 1st weeks closure (05/10/26 – 10/10/26) will be between A1067 Fakenham Road Roundabout and A140 Cromer Road
• The 2nd weeks closure (12/10/26 – 17/10/26) will be between the A140 Cromer Road and A1151 Wroxham Road Roundabout
• The 3rd weeks closure (19/10/26 – 23/10/26) will be between A1151 Wroxham Road and A1270 Postwick
This will ensure the work is complete before the Christmas Embargo and also hopefully will avoid the time of year when the poorer weather is expected. The alternative, lane closures throughout the days, avoiding the need for nighttime closures, has been investigated and discussed, however following a comprehensive cost analysis/programme schedule between both options (night closure/day lane closure), lane closures during the day has been discounted as a viable option.
We have applied for the durations given to allow for contingencies such as any bad weather events but would hope to complete each section in 3 or 4 days. The NDR will remain fully open and accessible during the day.
We are intending to have electronic signs placed strategically on the network to keep the public fully informed, as well as full visibility diversion signs to ensure people can still travel around easily. Our Comms team will also be advised so social media will be updated to inform as many people as possible. The roundabouts will remain open to allow traffic to still cross the NDR.