23/06/2026
π£ M27 Update π£
This morning all four lanes of the M27 Junctions 5 to 7 reopened as National Highways has now completed the technology testing and the concrete resurfacing works. Variable speed limits are in place.
As part of the scheme, they have:
π overlayed the concrete surface with 89,907 tonnes of low-noise asphalt
π excavated 11,661m3 of earth
π installed 9,460 of concrete barrier
π installed 5,912m of non-concrete barrier
π repaired or replaced 11,289m of drainage
π sealed 78,543m of joints between concrete bays
π replaced 281 concrete bays
π completed 1,100 concrete repairs
π installed 6,308 road studs
β On Tuesday 30th June the M3 southbound to M27 eastbound link road will be closed overnight (9pm-6am).
Diversion:
continue northbound on the M3
exit at junction 13
follow the A335 to the A27
travel eastbound to M27 junction 7
join the M27 eastbound carriageway
Dates may change due to weather or operational needs.