19/06/2026
🚧 Upcoming Highway Works – Week Starting 22nd June 2026 🚧
Please take note of the scheduled works across the city and plan your journeys accordingly:
🔧 Pothole Pro Works
The Pothole Pro will be carrying out small patch repairs to the carriageway.
These include:
• 22/06-24/06- Baddeley Hall Road- Baddeley, Milton and Norton
• 25/06-26/06- Escape Road onto Baker Crescent- Baddeley, Milton and Norton
🛣️ Carriageway Resurfacing
Works to improve carriageways in the city continue this week. Schemes include:
• Botteslow Street (Potteries Way to Melville Street)
Future carriageway resurfacing schemes (dates subject to change depending on completion of other surfacing projects or adverse weather conditions):
• Dawn Avenue
• Sherratt Street
• Meir View
• Aquinas Street
🛣️ Carriageway Surface Treatment
Surface Dressing Phase 2 – lock treatment:
• Leek Road (Limekiln to North Drive)
• High Street (Reginald Mitchell Way to Woodstock Street)
• Eastern Rise
• Tony Waddington Place
• Gordon Banks Drive
• George Eastham Avenue
• Dennis Viollet Avenue
🚦 Traffic Signal Works
Times Square Traffic Signal Upgrade - work commences Monday 22nd June until Spring 2027
🚌 Non-Highway Projects
Schemes include:
• Longton Public Realm- works continue for several weeks
• South Wolfe Street- works continue for several weeks
Accessible bus stop improvements:
• 22/06-23/06- Grosvenor Road- Highfield Avenue bus stop
• 25/06-25/06- Grosvenor Road- David Road bus stop
• 26/06-27/06- Waterhead Road- Bartholomew Road bus stop
🛝 Playground Projects
Work commencing Monday 22/06/2026.
• Repainting Foley Park playground.
• Repainting Drive Park playground.
Sports court remarking Bentilee and Ubberley / Foley Park MUGA. Orders to be placed with contractor.
• Grange Park, cleansing works and repainting.
• Middleport Park, repair to grass matts beneath zip line.
We appreciate your patience and cooperation as we continue to improve local roads and infrastructure. 👷♂️🚗