28/08/2026
As youโll probably have seen, Marlborough Road has now fully reopened in both directions โ great news ๐
Wales & West Utilities will need to pop back to finish the surfacing at some point over the next couple of weeks, but weโre told that the road will not need to be closed for this.
Now Marlborough Road is open again, W&W will be moving to the next stage of the works.
This will be:
๐ Swindon Road (between Berkeley Road and Perrys Lane)
๐
1 September to 13 September
After that, they'll be at:
๐ Moormead Road (roughly from the Prospect to the Co-op roundabout)
๐
14 September to 4 October
Temporary traffic lights will be in place on these last two sections.
If you have any questions, email Swindon Borough Council on [email protected]
Thanks, everybody ๐