What: SCHEDULED WATER INTERRUPTION
- SHUTDOWN OF PUMP HOUSE – BALANGOBONG PUMP HOUSE 1 (BPH 1)
When: SEPTEMBER 4, 2023, 9:00AM TO SEPTEMBER 8, 2023, 10:00PM
Why: WELL REHABILITATION AND MAINTENANCE WHICH COVERS THE FOLLOWING ACTIVITIES:
1. Day 1 – Mobilization and pull out of riser pipes, well-casing, submersible pump and submersible motor
2. Day 2 – Camera logging and brushing of well
3. Day 3 – Well cleaning using air compressor (12hrs)
4. Day 4 – Camera logging, (well disinfection using chlorine) and re-installation of submersible pump and motor, riser pipes, and well-casing; start of pumping test
5. Day 5 – End of pump test (starts feed to transmission line); demobilization
Affected Areas:
LOW WATER PRESSURE TO NO WATER
1. Parts of Palamis and Poblacion (Western side of Marcos Avenue and parts of Sadsaran)
2. Pogo
3. San Jose
4. San Roque
5. Landoc
6. Polo
7. Tawin-tawin
8. Inerangan
9. San Antonio
Please save enough water for your consumption during this period.