The Building Maintenance Team completed its work for the week (July 21 - 26, 2025).

SECTIONS:

Air-conditioning:
• Repaired and troubled shot of the window-type aircon and changed the capacitor of the floor-mounted aircon at CHO – Sanitary Section.
• Charged freon to 2-unit split-type aircon at MISO.
• Installed aircon drainage at CSWS (Children & Youth).
• Charged freon to 1-unit wall-mounted split-type aircon at OPD – CHO.
• Cleaned 1-unit split-type aircon at BM office.
• Charged freon at MCPO.
• Troubled shot and charged freon to 1-unit floor-mounted split-type aircon at Public Market (OPCEN).
• Troubled shot and charged freon of 2-unit split-type aircon at the Police Clearance office.
• Cleaned 4-unit floor-mounted aircon at the Vice Mayor’s office and the City Assessors office.

Carpentry:
• Dismantled cubicles at the City Legal office.
• Repaired ceiling of Motorpool office.
• Installed tiles at CHO Cr.
• Assembled 1 office table at CEO.
• Installed ceiling at CHO Cr.
• Renovation of Daycare Center at MGLP.
• Repaired ceiling at MCENRO office.
• Cutting of woods for the Engineering office.
• Renovation of Daycare Center at MGLP.
• Installed sealant at the entrance door and repaired tiles at City Hall.
• Installed metal parring at CHO Cr.
• Installed sealant at sliding window at CHO (Dr. Catulong’s office).

Electrical:
• Pulled out convenience outlet at old City Legal office.
• Replaced busted bulb at City Nutrition office.
• Installed decorative lights at Plaza ground.
• Replaced busted bulb and fluorescent tube at Command Center.
• Repaired fluorescent diffuser at SP office.
• Pulled out and condemned electrical lighting due to damage to the ceiling at MCENRO.
• Installation of convenience outlet & provision of power source for Led wall TV at PESO office.
• Repaired aircon outlet and replaced busted lamp at Motorpool office.
• Replaced busted Led bulb and Led tube at SAMHSO.
• Replaced busted bulb at BAC office.
• Activation of the generator set at the Parking building.
• Installed additional lights at the 2nd floor female CR at City Hall.
• Replaced busted bulb at SP office.
• Wired and installed a 60A switch for the electrical supply power source for the welding machine at MCC.

Painting:
• Painting of tables and repainting of the Motorpool office.
• Skim coating of ceiling at CHO Cr.
• Repainting of the Motorpool office.
• Painting of office table at Motorpool for Mayor’s office.
• Painting of CHO Cr.

Plumbing:
• Repaired lavatory and downspout at Cong. Office.
• Repaired artesian well at Sitio San Jose, Brgy. Jagobiao.
• Repaired artesian well at Sitio Sto. Rosario, Purok Goma, Brgy. Jagobiao.
• Repaired artesian well at Sitio Lourdes, Brgy. Jagobiao.
• Repaired artesian well at Sitio Sliding Hills, Brgy. Labogon.
• Repaired artesian well at Sitio Sta. Cruz, Purok Diamond, Brgy. Jagobiao.

Welding:
• Ongoing fabrication and installation for school expansion of MCC.

To our immediate heads, thank you. Engr. Marivic Cabigas, Department Head, Engr. Lee S. Naya, Division Chief; Mr. Dominador A. Ermac, Assistant Division Chief; AR. Francis P. Cabigas, Admin Chief.
Especially to Section Chiefs and section personnel.

These are the completed tasks in the following sections on building maintenance this week (July 14 - 19, 2025).SECTIONS:...
21/07/2025

These are the completed tasks in the following sections on building maintenance this week (July 14 - 19, 2025).

SECTIONS:

Air-conditioning:
• Cleaned, repaired, and charged freon of 6-unit window-type and split-type aircon at TEAM offices.
• Replaced 1-unit capacitor of floor-mounted split-type aircon at CEO.
• Repaired 1-unit circuit board of window-type aircon at Room 9 (TB-DOT) of CHO.
• Troubleshot and replaced thermostat of 1-unit window-type aircon at CD’s office of MCPO.
• Charged freon to 1-unit wall-mounted split-type aircon at Supply Room of MCPM.
• Checked aircon due to leaking at the Mayor’s office.

Carpentry:
• Assembled a cubicle at the SP office.
• Assembled 2-unit office tables at the City Legal office.
• Assembled office table at Mayor’s office.
• Make an office table for the Mayor’s office at the Motorpool.
• Replaced 4 pcs doorknob at Cong office.
• Assembled 2-unit office table at Legal office.
• Repaired downspout due to leaking at CEO.
• Installed signages at the Parking Building.
• Installed tiles at CHO Cr.
• Installed a new ceiling and repaired table drawers at the DGS office.
• Installed ceiling at CHO Cr.

Electrical:
• Replaced the busted fluorescent light and installed 7 sets at CDRRMO.
• Inspected all electrical loads at City Hall Building for safety purposes.
• Replaced a busted Led bulb at BM office.
• Replaced a busted Led bulb and fluorescent Led tube at BPLO office.
• Wired and installed a convenience outlet at the Congress office.
• Wired and installed outlets and pin lights at CHO Cr.

Painting:
• Lettering of parking signage for the Annex building at Motorpool.
• Skim coating of door for City Library and table for CMO at Motorpool.
• Painting of tables for Mayor’s office and door for City Library.
• Ongoing painting of tables for the Mayor’s office, the door for the Public Library, and the ceiling for the DGS office.

Plumbing:
• Ongoing repaired water supply, lavatory, and urinal at MCSAPO.
• Repaired downspout due to leaking at CEO.
• Prepared for installation of lavatory and bowl at CHO Cr.

Welding:
• Fabricated 2-unit cover for window-type aircon at BM grounds.
• Fabricated boom bar for Public Market and MCC at BM grounds.
• Fabricated and installed boom bar at Public Market.
• Assembled boom bar at Public Market (Exit area).
• Demolition of the existing concrete slab in preparation for the installation of foundation works for the expansion of MCC.

To our immediate heads, thank you. Engr. Marivic Cabigas, Department Head, Engr. Lee S. Naya, Division Chief; Mr. Dominador A. Ermac, Assistant Division Chief; AR. Francis P. Cabigas, Admin Chief.
Especially to Section Chiefs and section personnel.

Last week all sections of Building Maintenance accomplished the following task (July 7 - 12, 2025).SECTIONS:Air-conditio...
14/07/2025

Last week all sections of Building Maintenance accomplished the following task (July 7 - 12, 2025).

SECTIONS:

Air-conditioning:
• Installed power supply of 1-unit wall mounted aircon at VIP room of the Sports Complex.
• Repaired 1-unit floor mounted split type aircon at HRMO.
• Repaired aircon drainage of 1-unit split-type aircon at SP office.
• Inspected and repaired the aircon unit at the Accounting office.
• Repaired and charged freon and clogged up aircon units at Market, MISO, and Command Center offices.
• Cleaned 3-unit wall-mounted aircon at the Mayor’s office.

Carpentry:
• Ongoing installation of tiles at CHO Cr.
• Ongoing installation of ceiling at CHO Cr.
• Hauling of cement for CHO Cr.
• Repaired the cubicle and installed tiles at the Vice Mayor’s office.
• Repaired and installed tiles at the SP office.

Electrical:
• Assisted and standby at the Sports Complex for sound system backed up for City Inaugural event.
• Replaced busted lights at the CSWS office.
• Installed round recessed slim down light at Mayor’s office.
• Replaced the defective safety breaker for the aircon unit at the Accounting office.
• Troubleshot a convenience outlet at the SAMHSO office.
• Wiring installation at the Admin Office.

Painting:
• Ongoing repainting works at the Sports Complex.
• Repainting at CTO.
• Cleaned the working area at the Motorpool.

Plumbing:
• Repaired urinal at the City Hall Men’s Cr.
• Replaced water pump at Tipolo Elementary School.
• Repaired artesian well at Purok Sambag, Brgy. Ibabao.
• Installed a water source at the Mayor’s office for lavatory and CR supply.

Welding:
• Fabricated and assembled of fence at MCENRO (North Bus).
• Pulled out welding materials at MCENRO (North Bus).
• Cleaned and arranged welding materials at BM grounds.
• Fabricated window and door grill for City Library.
• Fabricated and installed a window and door grill at the City Library.
• Cleaned and arranged welding materials at BM grounds.

To our immediate heads, thank you. Engr. Marivic Cabigas, Department Head, Engr. Lee S. Naya, Division Chief; Mr. Dominador A. Ermac, Assistant Division Chief; AR. Francis P. Cabigas, Admin Chief.
Especially to Section Chiefs and section personnel.

The Building Maintenance Team completed its work task this week (June 30 – July 5, 2025).SECTIONS:Air-conditioning: • On...
07/07/2025

The Building Maintenance Team completed its work task this week (June 30 – July 5, 2025).

SECTIONS:

Air-conditioning:
• Ongoing repaired and charged with freon at the Sports Complex.
• Cleaned the 3-unit aircon at the Accounting office.
• Repaired and troubleshot the aircon unit at the Sports Complex.

Carpentry:
• Assembled conference table at Annex Building.
• Assembled 2-unit office table at DGS conference room.
• Ongoing installation of tiles at CHO Cr.
• Hauling of plywood’s and installation for CHO Cr ceiling.
• Repaired the ceiling at the Sports Complex.
• Repaired tiles at VIP room CR at the Sports Complex.

Electrical:
• Replaced busted bulb at City Hall Admin Office.
• Wiring and installation of bulb at the Sports Complex.
• Wired and installed 2 downlight bulbs at City Treasurers office.
• Replaced busted bulb and switch at the City Mayor’s office.
• Installed a 3-gang switch and a single switch at CHO.
• Wiring and installation of a breaker for the supply electrical power source for the welding machine at the North Bus Terminal.
• Installed bulb at tent for the Plaza ground event.
• Installed outlets at the Mayor’s office.

Painting:
• Ongoing repainting works at the Sports Complex.

Plumbing:
• Re-piping of water supply pipeline at Mandaue City Library.
• Repaired artesian well at Purok Tambis, Brgy. Casungtingan.
• Repaired electric water pump at Tipolo Elementary School.
• Repaired the water closet and checked the water supply at the Mayor’s office.

Welding:
• Repaired railings at the Sports Complex.
• Assisted in scaffolding installation for electrical use.
• Arranged welding materials at BM grounds.
• Assembled rack for welding materials at BM grounds.
• Fabricated and installed fence at the North Bus.

To our immediate heads, thank you. Engr. Marivic Cabigas, Department Head, Engr. Lee S. Naya, Division Chief; Mr. Dominador A. Ermac, Assistant Division Chief; AR. Francis P. Cabigas, Admin Chief.
Especially to Section Chiefs and section personnel.

Address

Plaridel Street
Mandaue City
6014

Opening Hours

Monday 8am - 5pm
Tuesday 8am - 5pm
Wednesday 8am - 5pm
Thursday 8am - 5pm
Friday 8am - 5pm

Website

Alerts

Be the first to know and let us send you an email when DGS Building Maintenance posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Share