09/04/2026
PROJECT UPDATES: Marshall almost ready for paving
Valley Avenue and Marshall Street reconstruction (photo): This past week, crews completed replacements of water and sewer services on Valley Avenue from Johnson to High Street. The rock base for the new pavement is complete on Marshall and Johnson. The contractor plans to place new curb, gutter and concrete pavement on Marshall next week. Crews also plan to replace the storm sewer on Valley from Johnson to High Street.
Residential streets: Concrete sidewalk and driveway replacements are complete in the area of Clark Street, Water Street and Adams Avenue. Crews are replacing sidewalks on St. Joseph, James and Frank avenues, and concrete work should be done this week. Crews plan to replace sod next week.
Sorensen Road watermain replacement: Crews plan to continue watermain replacement north of Hammer Road.
Keep following us for updates.