07/21/2026
There've been a lot of posts everywhere about the proposed data center here in Amherst, so I thought it might be easier to keep everything in a dedicated post. Feel free to ask your questions, post your concerns, whatever makes you happy, and I'll try to answer what I know.
A few things I want to point out first:
- I am not for or against the proposal at this point. I simply need more information to make an informed decision, if it even comes to council in the future.
- this hasn't gone through any approval process yet. The Zoning Board of Appeals meeting on July 29th at 6:30pm is the first vote of multiple, so nothing has been finalized yet.
- the proposal isn't one of the giant data centers we hear about on the news
- they want to reuse the existing Nordson buildings
- they would not use a lot of water. The cooling system would be a closed loop water cooling system that gets refilled once every 10 years.
- no information on electrical usage. Nordson was supplied by First Energy, not Amherst, and it's unknown which supplier the data center would use or what their usage would be
- they plan to take pre and post construction noise level studies, including adding sound mitigation systems if needed
Edits with updated information:
- the variance for the data center is for the addresses 100, 200 and 300 Nordson Drive, and the buildings they're tearing down are 444 Gordon and 555 Jackson. While the timing of tearing down some buildings right when the data center is proposing to use other buildings is INCREDIBLY bad the two things are unrelated.
- I was reading some news articles and a few mentioned the data center might be 45MW. The developer wouldn't answer my question when I asked him that directly.
- I was reading the real estate documents for the Nordson properties and found an interesting tidbit. Even if sold the properties at 100 and 200 Nordson Drive are to be leased back by Nordson through 2028.
The Amherst Board of Zoning Appeals will decide next week whether a proposed data center at the former Nordson property can move forward to the next stage of the city's review process.