10/20/2023
Update #14 on Strawbridge:
Drywall is hung and finished in the basement, will resume hanging in the social hall and sanctuary next week. Extensive plaster repair work begins in the sanctuary next week. Cabinets and trim will arrive in November for installation. Painting is scheduled to begin at the end of November.
We will likely need to block a section of Jenkins Alley for a few hours in November in order to lift structural steel and HVAC units to the roof of the Carriage House. The date will be posted on this page when it's scheduled.