08/07/2023

Where are your grader operators today?

Team 1: Claude Rd to Railroad Ln

Team 2: Honey Suckle Rd to Spotted Fawn Rd

Team 3: Whitetail Way to Little Frank Rd

08/03/2023

Where are your grader operators today?

Team 1 — Diamond G RD to Arbor RD

Team 2 — Richard King Road, to Poplar Rd.

Team 3 — Clark RD to Whitetail way

Mershon Road head wall restoration project 60% completed.
08/01/2023

Mershon Road head wall restoration project 60% completed.

Please report down trees blocking roadways to 911. Road Crews have been conducting route clearance operations in tandem ...
06/15/2023

Please report down trees blocking roadways to 911. Road Crews have been conducting route clearance operations in tandem with the Fire Department. Stay safe and sheltered during these storms.

6/15/23
Showers and thunderstorms will become numerous today and tonight with a potential for some storms becoming strong to severe across SE GA and NE FL this afternoon and evening. Main impacts will be damaging winds and heavy rainfall.

The Pipe crew cleaned outfalls and blew out pipes on Brown Branch today.
03/29/2023

The Pipe crew cleaned outfalls and blew out pipes on Brown Branch today.

Mill Branch Box Drainage Project 100% completed.
03/28/2023

Mill Branch Box Drainage Project 100% completed.

Graders have been steadily fixing roads and pulling ditches as they go. When there is no ditch, the road becomes the dit...
03/23/2023

Graders have been steadily fixing roads and pulling ditches as they go. When there is no ditch, the road becomes the ditch. Installing ditches keeps water off of our roads. While this is time consuming, we are assuring we have less problems within the roadbed. Less problems mean our graders can move faster and get to roads in a more timely manner.

03/22/2023

Bush machines are steady clearing the right of way ahead of graders so ditches can be reclaimed.

Cathleen Drive project is at 90% and road should be open to traffic by Thursday afternoon.
03/22/2023

Cathleen Drive project is at 90% and road should be open to traffic by Thursday afternoon.

Mill Branch drainage project is 80% completed.
03/22/2023

Mill Branch drainage project is 80% completed.

Ramah Church Road drainage project is coming to a close.
03/22/2023

Ramah Church Road drainage project is coming to a close.

The tractor is out today trying to smooth the travelled way until graders can get caught up.
03/20/2023

The tractor is out today trying to smooth the travelled way until graders can get caught up.

Address

602 W. Carter Avenue
Blackshear, GA
31516

Opening Hours

Monday 7am - 5pm
Tuesday 7am - 5pm
Wednesday 7am - 5pm
Thursday 7am - 5pm

Telephone

+19124492030

Alerts

Be the first to know and let us send you an email when Pierce County GA Road Department posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Pierce County GA Road Department:

Share