🚧 South Street Project Update: The End Is Near! 🚧
This is a BIG one! All concrete work on the South Street Reconstruction Project is officially complete! 🎉 Yard grading behind the new sidewalks has also been completed, and grass will be planted tomorrow, Saturday, September 26th.
Next week brings one of the final major stages of the project. Wagner Paving will be on South Street Monday and Tuesday to fine-grade the road surface in preparation for asphalt paving later in the week. Residents in the project area will need to have their vehicles out of their driveways by Monday morning so crews can complete this work and prepare for paving.
Once asphalt work begins, paving will take a minimum of two days, with at least one day for the base course and another for the surface course. The good news is that the road will be drivable shortly after the asphalt is placed, so access should return relatively quickly as each phase is completed.
After paving, only one major piece remains: the new street lights!
After months of water mains, storm sewer, dirt, concrete, rain delays, curbs, sidewalks, grading, and a whole lot of patience... THE END IS NEAR! 🏁
Thank you to our South Street residents and everyone in the community for your patience and cooperation throughout this project. We are excited to see the new South Street coming together!