08/08/2026
Another major milestone is coming for the Woodstock Bridge project.
On Tuesday morning, August 11, Evroks is scheduled to begin tensioning the bridge's new cables. This important step follows weeks of work removing the existing cable ties, preparing the arch connections, installing the new cable system, and completing other structural work.
Evroks has also been installing composite scuppers and forming the new lightweight concrete deck over steel exodermic panels as work continues on the bridge.
Check out the latest photos to see the progress being made.