10/13/2026
FOR IMMEDIATE RELEASE
Hardin County Judge/Executive Keith Taul signed a contract today to repair the historic White Mills Truss Bridge on Old 84 State Highway, which has been closed since earlier this year due to damage.
"Under the leadership of Senior Engineer Mark Absher, the County has coordinated with contractors and the Kentucky Transportation Cabinet to identify and plan the necessary repairs," Taul said. "The project is estimated to cost up to approximately $90,000, with 80% of eligible costs reimbursed through the state’s 80/20 funding program. Repairs are expected to be completed within 60 days and will restore the bridge for vehicle traffic, with reopening anticipated by the end of 2026."
Absher said there were numerous ways the repairs could have been handled, but ultimately going forward with this approach made the most sense.
"We looked at several different options in addressing the issues at White Mills Bridge. The bare minimum was to replace the two failed members. But in looking at the bridge characteristic we are going to be proactive and replace two members directly across from the failed members, along with the two failed members," Absher said. "This additional repair is with concurrence from state. The goal is to make it to where vehicles can use it again, pending state approval, and to improve the longevity of the bridge by proactively replacing four members.”
Taul said his sincere hope is the bridge will be ready in time for the annual Christmas lighting, a tradition that has been popular for many years.