09/06/2026
The General Authority of the City of Franklin MH-A-108 Sewer Project tentative schedule for the week of 9/8/2026:
*Work schedule is Tuesday – Friday due to holiday
Contract S-1 (Bison Construction, Inc.)
Continue lateral excavation & prep for waterline on Grant
Traffic impact:
Grant: 100 block / Work area with flaggers (prep)
Grant: 600 block / Work area with flaggers (laterals)
Contract S-2 (Mortimer’s Excavating, Inc.)
Prep for pipe bursting on 14th
No subcontractors scheduled this week
Traffic impact:
14th: Liberty – Franklin / Road closures & "No Parking" restrictions
Elk & Otter: 13th – 15th / Road closures & "No Parking" restrictions
Contractor met with school officials: School buses will be permitted to turn onto 14th & onto Elk