This Week (August 31 to September 4): Concrete crews began pouring pavement in side road intersections between Railroad ...
09/03/2026

This Week (August 31 to September 4): Concrete crews began pouring pavement in side road intersections between Railroad Street and Cedar Street. The contractor poured curb & gutter in intersections on the west side of WIS 22 between West Park Street and West Cedar Street. Crews poured concrete sidewalks and driveways along the east side of WIS 22 between Railroad Street and WIS 32. Topsoil work was completed around asphalt driveways between Finnegan Lake Road and East Main Street.

Next Week (September 7 to September 11): The concrete paving contractor will complete concrete pavement pours in intersections between Railroad Street and East Cedar Street. Crews will remove existing sidewalk on the west side of WIS 22 between East Main Street and WIS 32. Concrete crews will begin pouring new sidewalks and driveways along the west side of WIS 22. The contractor will begin placing topsoil around new sidewalks and driveways on the east side of WIS 22 between East Main Street and WIS 32.

Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o Driveways on the east side of WIS 22 between East Main Street and WIS 32 are closed for concrete paving operations.
 Access to driveways on the west side of WIS 22 between East Main Street and WIS 32 was temporarily reinstated this week. These driveways will be closed the week of September 7 for sidewalk work.
 Driveways on the east side of WIS 22 between East Main Street and WIS 32 will opened the week of September 7.
o Property owners on both East Cedar Street and West Cedar Street can continue to access their homes from either Washington Street or WIS 32.

Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.



Luke Hardinger, PE
Project Engineer

QUEST Civil Engineers, LLC - Construction, Surveying, Design and Environmental Solutions. Locations in Wisconsin Rapids, WI, Green Bay, WI, Rice Lake, WI

09/01/2026

Oak Street will be closed tomorrow 9/2 to thru traffic but accessible from both entrances. City Public Works and Water/Sewer need to replace a water pipe. Work will begin at 8am until 3pm.

08/27/2026

For residents living on Highway 22/West Main Street between Finnegan Lake Road and East Main Street where the roadway construction project has restored and replanted grass in front of your home. You are encouraged to begin mowing the newly planted grass at your earliest convenience. Mowing will help with w**d control. The straw netting that was placed at the time of planting can be removed in locations where the grass is growing well prior to mowing.

Send a message to learn more

08/27/2026

This Week (August 24 to August 28): The contractor completed pouring curb & gutter along the west side if WIS 22 between East Main Street and WIS 32. Concrete pavement crews poured the parking lane between East Park Street and Washington Street along the northbound lane. The curb crew poured concrete curb & gutter in intersections on the east side of WIS 22 between Railroad Street and East Cedar Street. The contractor began grading and setting form work for sidewalk on the east side of WIS 22 between Railroad Street and WIS 32.

Next Week (August 31 to September 4): The concrete paving contractor will set up and begin pouring concrete pavement in intersections on the east side of WIS 22 between Railroad Street and East Cedar Street. Crews will pour curb & gutter in intersections on the west side of WIS 22 between West Park Street and West Cedar Street. Sidewalk pours will begin along the east side of WIS 22 between Railroad Street and East Cedar Street. The contractor will complete topsoil work around asphalt driveways between Finnegan Lake Road and East Main Street.

Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o Driveways on both sides of WIS 22 between East Main Street and WIS 32 are closed for concrete paving operations.
 Access to driveways on the west side of WIS 22 between East Main Street and WIS 32 will be temporarily reinstated next week with gravel.
 Driveways on the east side of WIS 22 between East Main Street and WIS 32 will remain closed next week for concrete sidewalk and driveway work.
o Property owners on both East Cedar Street and West Cedar Street can continue to access their homes from either Washington Street or WIS 32.
o WIS 22 between East Main Street and Washington Street is completely inaccessible due to concrete pavement operations.

Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.

Luke Hardinger, PE

08/24/2026
08/20/2026

This Week (August 17 to August 21): The contractor placed shoulder gravel between Finnegan Lake Road and Harding Avenue. Concrete crews paved the southbound lane of WIS 22 between East Main Street and WIS 32. The contractor will begin pouring curb & gutter on the east side of the roadway for the northbound lane between East Railroad Street and WIS 32.

Next Week (August 24 to August 28): The concrete paving contractor will complete placement of curb & gutter on the west side of WIS 22 along the southbound lane of the roadway. Concrete crews will begin pouring curb & gutter in intersections between East Railroad Street and Cedar Street. The contractor will begin pouring concrete sidewalk on the east side of WIS 22 between Washington Street and WIS 32.

Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o Driveways on both sides of WIS 22 between East Railroad Street and WIS 32 are closed for concrete paving operations.

Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.

Thanks,

Luke Hardinger, PE
Quest Civil Engineers

08/17/2026

Good morning, we are doing maintenance on the siren and it will go off for about 15 seconds within the next half hour. Just a test!

08/13/2026

This Week (August 10 to August 14): The contractor backfilled new concrete work at the Christie Brook box culvert. Paving crews placed asphaltic pavement in intersections between Finnegan Lake Road and South McKenzie Avenue. The concrete contractor completed prep work in the northern half of the project between East Main Street and WIS 32 and will pave the northbound lane of concrete pavement this Saturday. Landscaping crews will complete restoration and placement of signing between Finnegan Lake Road and East Main Street.

Next Week (August 17 to August 21): The concrete paving contractor will pave the southbound lane of concrete pavement between East Main Street and WIS 32. Curb & gutter work will begin in intersections between East Railroad Street and WIS 32.

Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o All driveways between Finnegan Lake Road and East Main Street are now open.
o Driveways on the east side of WIS 22 between East Railroad Street and WIS 32 will be closed this week Saturday when northbound concrete paving operations begin. The contractor will provide written notice with information about accessibility.
o Driveways on the west side of WIS 22 between East Railroad Street and WIS 32 will be closed beginning in the middle of the week next week for southbound concrete paving operations. The contractor will provide written notice with information about accessibility.

Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.


Luke Hardinger, PE
Project Engineer
Quest Civil Engineers, LLC

Send a message to learn more

08/12/2026

This Week (August 10 to August 14): The contractor backfilled new concrete work at the Christie Brook box culvert. Paving crews placed asphaltic pavement in intersections between Finnegan Lake Road and South McKenzie Avenue. The concrete contractor completed prep work in the northern half of the project between East Main Street and WIS 32 and will pave the northbound lane of concrete pavement. Landscaping crews will complete restoration and placement of signing between Finnegan Lake Road and East Main Street.

Next Week (August 17 to August 21): The concrete paving contractor will pave the southbound lane of concrete pavement between East Main Street and WIS 32. Curb & gutter work will begin in intersections between East Railroad Street and WIS 32.

Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o All driveways between Finnegan Lake Road and East Main Street are now open.
o Driveways on the east side of WIS 22 between East Railroad Street and WIS 32 will be closed when concrete paving operations begin. The contractor will provide written notice with information about accessibility.

Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.

Send a message to learn more

08/10/2026

The City of Gillett received grants for the park which had timelines for things to be done. The City understands the concern about the fair with the play ground construction. The City Council met with the Fair Board to discuss the up coming fair to make sure everything runs smoothly. They also discussed future ideas for the fairgrounds/park. Before the fair, the construction area will be shrunk down to the footprint of the playground and all equipment will be moved out of Zippel Park. The City of Gillett is dedicated to working with the fair during these tough times of construction and looks forward to working together to bring the fair to the City of Gillett for years to come.

Address

150 N McKenzie Street
Gillett, WI
54124

Opening Hours

Monday 8am - 4pm
Tuesday 8am - 4pm
Wednesday 8am - 4pm
Thursday 8am - 4pm
Friday 8am - 12pm

Telephone

+19208552255

Alerts

Be the first to know and let us send you an email when City of Gillett posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share