09/03/2026
This Week (August 31 to September 4): Concrete crews began pouring pavement in side road intersections between Railroad Street and Cedar Street. The contractor poured curb & gutter in intersections on the west side of WIS 22 between West Park Street and West Cedar Street. Crews poured concrete sidewalks and driveways along the east side of WIS 22 between Railroad Street and WIS 32. Topsoil work was completed around asphalt driveways between Finnegan Lake Road and East Main Street.
Next Week (September 7 to September 11): The concrete paving contractor will complete concrete pavement pours in intersections between Railroad Street and East Cedar Street. Crews will remove existing sidewalk on the west side of WIS 22 between East Main Street and WIS 32. Concrete crews will begin pouring new sidewalks and driveways along the west side of WIS 22. The contractor will begin placing topsoil around new sidewalks and driveways on the east side of WIS 22 between East Main Street and WIS 32.
Traffic impacts: WIS 22 closed to thru traffic for the duration of the project.
o Driveways on the east side of WIS 22 between East Main Street and WIS 32 are closed for concrete paving operations.
Access to driveways on the west side of WIS 22 between East Main Street and WIS 32 was temporarily reinstated this week. These driveways will be closed the week of September 7 for sidewalk work.
Driveways on the east side of WIS 22 between East Main Street and WIS 32 will opened the week of September 7.
o Property owners on both East Cedar Street and West Cedar Street can continue to access their homes from either Washington Street or WIS 32.
Detour: WIS 22 will remain closed and detoured. Detour route directs WIS 22 traffic to use County H and County R.
Luke Hardinger, PE
Project Engineer
QUEST Civil Engineers, LLC - Construction, Surveying, Design and Environmental Solutions. Locations in Wisconsin Rapids, WI, Green Bay, WI, Rice Lake, WI