08/31/2026
MnDOT will be repairing the bridge at Hwy 169 and Betty Crocker Dr, as well as another bridge nearby, beginning Monday, Aug 31. Evening and overnight road closures are planned for this work, which is expected to wrap up by Wednesday morning, Sept 2.
Full schedule:
8 pm Monday, Aug 31 through approximately midnight, Tuesday, Sept 1
• Northbound Hwy 169 will be closed between Minnetonka Blvd and Cedar Lake Rd.
• The Cedar Lake Rd ramp to northbound Hwy 169 will be closed.
• This work will allow crews to make repairs to the Cedar Lake Rd bridge over Hwy 169.
Approximately midnight through 5 am, Tuesday, Sept 1
• Once work is complete at Cedar Lake Rd bridge, northbound Hwy 169 will reopen at Cedar Lake Rd.
• Crews will then close northbound Hwy 169 between I-394 and Betty Crocker Dr, as well as the Betty Crocker Dr ramp to northbound Hwy 169.
• This closure is for crews to repair the Betty Crocker Dr bridge over Hwy 169.
8 pm Tuesday, Sept 1 through 5 am Wednesday, Sept 2
• Crews will again close northbound Hwy 169 between I-394 and Betty Crocker Dr and the Betty Crocker Dr ramp to northbound Hwy 169.
• This closure is for crews to finalize repairs on the Betty Crocker Dr bridge over Hwy 169.
https://www.goldenvalleymn.gov/AlertCenter.aspx?AID=Hwy-169-Overnight-Closures-Monday-Aug-31-68