05/29/2026
During my last DOTD post, I had several questions which I was able to get answers for. Please see DOTD responses below…
🔴What is the status of the traffic light at Company Canal bridge?
· Contractor has completed install and has requested inspection of the installed signal, with turn on expected next week.
🔴There have been some drainage concerns (water pooling on road) on LA 24, particularly just south of South Terrebonne High near Lecompte St. Will there be any drainage work done with this patching project?
· The work remaining on that area of LA 24 is striping and a high friction surface treatment on the Bourg Larose Hwy. There is no drainage work here included in this pavement project.
· I will get with our design group to see if there is any drainage type of funding available to do anything here.
🔴What is timeline to begin work on Prospect Blvd (LA 3087)?
· Project H.015816 from the Lift Bridge to the Overpass is scheduled to bid in July 2026.
🔴What is timeline to begin work on LA 56?
· Project H.015822 from Presque Isle to LA 58 (Marty J’s) is scheduled to bid in August 2026.