More traffic updates:
Roundabout and Bridge
BUR completed installation of the water main on Stratton Road and passed pressure testing Thursday morning. Stratton Road should be open normally Friday.
BUR moved their operation to Blake St. and will spend the remainder of this week and likely all of next installing water main there. They are also planning to have a second crew operating at the end of next week on River St. at the corner of Rt. 124 to install a large drainage structure and then complete some additional drainage crossings.
And thank you for your patience as the Peterborough Street Sidewalks are constructed.