08/24/2026
Evening,
Just wanted to give a heads up, tonight and tomorrow night our painting contractor will be in at 9pm to start painting the stop bars, stops, and crosswalks. The paint dries extremely fast, but if you see their truck and one of our Highway trucks please keep off the white paint. They will start the double yellow and fog lines in 2 weeks.
Also Wednesday and Thursday our crack sealing contractor will be back in crack sealing Evergreen Street, Clifton Dr development, Barbara Road, Sheridan Drive,and Prospect Street. That will occur from 7:30 am to 3pm.
I will send out an update within the next week with a milling and paving schedule.
Shawn