Update on Citywide Road Bond Intersection Improvements + Sanders and Benner: Delays & Increased Costs of Nearly a Half-Million
A few weeks ago, Mayor Yvonne Flores Cale and Mayor Pro Tem Michael Tobias brought forward an item asking the City to revisit all 2022 Road Bond and TIRZ intersection projects that were already underway, including intersections where extensive engineering work and land acquisition had already been completed.
Because this discussion has stretched across several meetings, I want to explain where things now stand and the costs that residents will bear.
As part of the 2022 Road Bond and TIRZ #2 improvements, the City spent nearly $1 million conducting detailed Preliminary Engineering Reports for these projects. Those reports evaluated traffic conditions, crash history, future demand, intersection alternatives, costs, right-of-way impacts, pedestrians and cyclists, and other factors before engineers made their recommendations.
The reports are publicly available on the City’s Road Bond website. Each report evaluated what type of intersection would be the most safe and durable longterm: in nearly all of them, roundabouts were clearly professionally recommended.
However, when this re-analysis was originally requested, there was very little discussion about its financial impact or what it could mean for the timelines of delivering better and improved roads for you.
We now have much more information.
Tonight, Council will be be voting on whether to spend an additional $478,638.51 to perform re-analysis. Of that amount, $393,616.79 will come from the 2022 Road Bond and $85,021.72 will come from TIRZ #2 funds.
The work will also happen in phases. The first three intersections to be re-evaluated will be:
• Lehman Road at Bunton Creek Road
• Center Street at Old Stagecoach Road
• Windy Hill at Cherrywood
The remaining 9 intersections will then be prioritized based on the Road Bond projects’ tentative bid and construction schedules.
After Phase 1, the results will come back to Council in groups of three or four intersections, and Council will give direction before the consultant moves into Phase 2 and develops a more detailed cost analysis. (More administrative delays.)
We are spending nearly another half-million dollars after already spending nearly $1 million studying these projects, and almost $394,000 of the new expense is coming directly from the 2022 Road Bond voters approved to make roadway improvements.
Council is aware that the 2022 Road Bond program is facing cost pressures, and staff has made it clear to Council that additional debt may ultimately be necessary to finish all of the projects. Every additional Road Bond dollar spent reanalyzing work we have already paid to analyze is a dollar that is no longer available for construction.
Then there is the cost of delay as these analyses and Phases are now being placed into a construction timeline that already had tentative bid and construction schedules. Construction costs can rise, contracts can become more expensive, and engineering or design work that has already been completed may have to be changed depending on what Council ultimately decides.
That means the real financial impact is not simply $478,638.51.
It is the cost of the new studies, the Road Bond dollars no longer available for construction, the potential cost escalation caused by delay, and potentially additional debt and interest if we eventually have to borrow more money to complete the projects voters already approved.
And residents experience that impact too, because they wait longer for improvements they were told were coming.
This is particularly concerning at Sanders and Benner along Kohlers Crossing, where engineers have already extensively evaluated signals and roundabouts and recommended roundabouts based on the overall analysis, including substantial safety benefits.
Just a few weeks ago, there was a serious crash at Sanders and Kohlers Crossing in which a vehicle flipped. Many others have posted about being hit at this intersection. Safety is on the line and here we are about to delay improvements.
Furthermore, funding for the Benner roundabout has already been removed from the proposed FY26 budget, while Sanders remains funded, even though Council has not formally decided to stop Benner improvements.
I support asking engineers difficult questions and have done so repeatedly in this process. Our own engineers have answered every question with expert knowledge and professional recommendations.
Council cannot endlessly restart the engineering process every time a new Council dislikes the conclusion reached by the last one. When this reanalysis was requested, residents were not shown that financial impact. Now we know what it costs and what it will delay.
I encourage you to email council at [email protected] or give public feedback tonight at 7pm at City Hall on your concerns.