08/28/2026
Green Bay Road Reconstruction: Good News! There will be no construction on Saturday, August 29.
Monday, August 31 – Friday, September 4
• Storm sewer installation will continue on Green Bay Road from West Center Avenue to the south. This work is expected to take two weeks. The road will be closed one block at a time as the work progresses south, ending at West Hawthorne Court.
• West Center Avenue will be closed on Monday, August 31 to complete the storm sewer work at that location. Residents should use Thornwood Lane to access IL Route 176.
Saturday, September 5 – Monday, September 7
• There will be no construction over the Labor Day weekend.
Looking Ahead: Week of September 8:
Storm sewer installation will continue.
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.