10/19/2026
đźš§ Centralville Construction Update | Week of October 19
Sewer, water, and drainage work continues over the next three weeks. Crews expect to continue drainage outlet and chamber work near VFW Highway, resume culvert installation on Bunker Hill Avenue, and continue installing the 60-inch stormwater pipe on Hildreth Street. Rock drilling on Ludlam Street will also continue.
Water main, hydrant, and valve work is planned at several locations. Stormwater pipe installation along the Willard Street–Beacon Street–Twentieth Street route is expected during the weeks of October 26 and November 2.
The 24-hour closures on Bunker Hill Avenue between West Sixth Street and Hildreth Street, and on Hildreth Street, will continue. Please follow posted detours and allow extra travel time. Dates may change.
View the full three-week construction look-ahead: https://lowellwater.com/2026/10/19/upcoming-construction-schedule-week-ofoctober-5-2026/