08/06/2026
Construction continued the Conewago Creek Restoration this week, finishing the work on the unnamed tributary, then starting on the main bank. Currently, work has been completed up to the halfway point of the south bank, where at times, up to 4 feet of legacy sediment had to be removed to restore the area to its historical floodplain levels. Work on this bank will continue up creek, where it will meet with the already completed phase three of the project. Once work on the south bank is complete, the same process will begin on the north side, working from phase three back down to Route 230 Bridge.