Argonne Road Corridor Improvement Project Community Update:
With equipment now arriving, crews are returning to complete the final installations on Argonne! What to expect over the next few weeks.
This week:
• Signal cabinet testing and inspections
• Pulling wire for signal cabinets
Weeks of January 26th – 30th and February 2nd – 6th:
• Traffic control setup
• Install handrail at City Hall ADA ramp
• Continue signal and lighting work
• Perform wiring, testing, and alignment of new signals
• Complete signal activation and lighting connections
• Final work on the concrete barrier adjacent to the trail
To safely complete this final phase of work, expect some short-term lane closures. While an effort will be made to minimize disruption, motorists should plan for occasional delays or slower travel.
We're in the home stretch! Thank you for your continued patience!