Progress continues on the Douglas County Justice Center, with the project remaining on schedule and on budget and completion estimated for spring 2027.
Here’s what’s been happening on site:
🔹 Half of the parking lot paving is complete, along with the trash enclosure and storage room.
🔹 The main roof and rooftop equipment are complete.
🔹 Second-story wall framing and first-floor sheetrock are finished, with interior painting underway.
🔹 Exterior metal siding installation is progressing.
👉 Want to see it for yourself? https://loom.ly/wHrZxFs
What’s next? Paving is expected to wrap up by Halloween, with security fencing, detention pond work, exterior finishes, and interior detailing continuing as construction advances.
📊 Project snapshot
Overall completion: 61.34%
Guaranteed Maximum Price: $47.92 million
Estimated completion: Spring 2027
The project team continues to monitor material availability and pricing while coordinating work to keep construction moving forward. Stay up to date on the Justice Center project and follow along as work progresses!