08/24/2026
North Lumpkin Street will see the east side parking lane shut down beginning today, August 24th as utility replacement and relocation work begins for the ongoing Transportation Alternative Program (TAP) project. Over the next few days and weeks, natural gas, water, electric, telecom, and storm will all be replaced/relocated for the project.
Keep in mind as well, sidewalks, lighting, etc. are continuing to see construction on North Broad Street as well, and once complete will move to North Lumpkin Street, and then a portion of Highland Avenue which will be the final stage of the project.
Transportation Alternative Program (TAP) projects, formerly Transportation Enhancement Program (TE) projects, are multi-year processes that begin with project applications, costing forecasts, engineering and construction design, environmental studies, easement acquisition, bidding, and finally construction.
The current TAP project, that began with the above process in 2019, encompassing North Broad Street, portions of East/West Highland Avenue, and North Lumpkin Street to include the construction of new and expanded sidewalks, street trees with landscaping, pedestrian lighting and other street furnishings, ADA accessible curb ramps, better defined pedestrian crossings, and storm water upgrades. The total cost estimate of this project is $3,879,119, with 80% being funded through the TAP grant (State) and SPLOST dollars covering the required local match of 20% of the project cost.
The original construction contract for this project, released in September 2025, is 540 days as approved by the Georgia Department of Transportation (GDOT). That puts the estimated completion as March 2027, weather allowances as a factor.