MAYOR DODGE’S ROAD CONSTRUCTION & INFRASTRUCTURE UPDATE
Neighbors,
I want to ensure our residents stay fully informed on the progress of the many roadway and infrastructure improvements happening throughout Orland Park. The Village continues to work in strong coordination with IDOT, Cook County, utility partners and private sector developers. This collaboration allows us to align construction timelines, reduce disruptions and maximize efficiencies across multiple corridors.
In Orland Park, the Village maintains your local neighborhood streets, while major roads are managed by the state or Cook County. State agencies handle roads like LaGrange Road, 159th Street, 143rd Street west of LaGrange and Wolf Road south of 143rd Street, while Cook County oversees 80th, 104th,108th Avenues and Will Cook Road.
While construction can be frustrating at times, each project plays a vital role in improving traffic flow, strengthening regional connectivity, modernizing aging infrastructure and supporting new economic development. These improvements ensure Orland Park remains a safe, accessible and thriving community for generations to come. Thank you for your patience.
Below is a snapshot of the major 2026 projects with estimated timelines. These timelines are weather dependent.
Village Road Program
• Catalina East & surrounding areas
Touch-up work and lawn restoration is estimated to be completed by Sept. 7. The top layer of smooth asphalt is estimated to be paved by Sept. 23, coordinated around school schedules.
• Ravinia Avenue Culvert Replacement (near Darvin Furniture)
Ravinia Avenue is closed near Darvin Furniture until approximately Sept. 18 so crews can replace an underground creek culvert.
• Orland Brook Drive (Wheeler Avenue to 159th Street)
Crews are currently replacing concrete along this stretch. It is estimated that complete full road rebuilding, including new asphalt, curbs, sidewalks and wheelchair-accessible ramps will be completed by Sept. 23.
• West Avenue (143rd Street → 151st Roundabout)/El Cameno Re’al Drive/80th Ave. –
Work is scheduled to begin mid-September and is estimated to be completed by Oct. 23. Crews will scrape off old asphalt, lay down a new road surface, and repair curbs, sidewalks, and wheelchair-accessible ramps.
Cook County Projects
• 104th Avenue (167th Street → 179th Street) – Substantially completed. Minor items remain.
Improvements included pavement resurfacing, culvert repairs, traffic signal upgrades and new wheelchair-accessible sidewalk ramps.
• 151st Street (Will Cook Road → Wolf Road) – Completed.
Project complete. Work included resurfacing the road and upgrading sidewalk ramps for wheelchair accessibility.
• 153rd Street (Wolf Road → West Avenue)
Crews still need to paint permanent lane lines, install pavement reflectors, repair underground traffic signal sensors and complete minor touch-ups. Major work is expected to wrap up by Oct. 30.
• 80th Avenue (151st Street → 170th Street)
Sealing pavement seams and repairing underground traffic sensors will continue through Sept. 11 before work shifts to repairing 75 manholes. Barricades and lane closures will be removed in sections as each manhole is finished, with all work expected to wrap up by Oct. 2.
• Wolf Road (North of 143rd Street)
Much of the road work is complete except near 143rd Street where crews still need to repair top-layer pavement flaws, lane line reflectors, final striping and final touch-up items. Substantial completion date is Oct. 30.
• 108th Ave. (143rd Street → 153rd Street)/179th (Wolf Road → La Grange Road)
This project is out for bid, with work expected to wrap up by Nov. 1. Work includes patching damaged asphalt at various locations.
Illinois Department of Transportation (IDOT) Projects
• Southwest Highway (Will Cook Road → Wolf Road) - Completed
Project complete. Work included repaving the road with a fresh layer of asphalt and installing wheelchair-accessible sidewalk ramps.
• Southwest Highway (131st Street → 135th Street)
Work has been delayed as IDOT, through its contractor and consultants, works through unforeseen geotechnical issues. The Village is working with IDOT to provide an updated schedule that can be shared with the public. More to follow.
• John Humphrey Drive & 143rd Street Intersection
Ongoing coordination continues with utility partners regarding relocation and staging. Some utilities have been relocated and sheet pile installation is expected to start in the coming weeks.
Costco Roundabout & Ravinia Avenue Extension
Construction of the new full-size roundabout serving Costco and the surrounding commercial corridor is underway, with detours and lane shifts expected. Work includes upgraded access, added lanes, and improved traffic flow. Completion is anticipated later this year.
This project is part of a broader corridor improvement plan, including the extension of Ravinia Avenue to 161st Street. Significant progress continues on this extension, which will add five lanes, a new traffic signal at 161st Street, dual left turn lanes, upgraded truck access and roadway improvements supporting Amazon Retail, Pulte Homes and Costco. Construction is anticipated in 2026.
Looking Ahead to Next Year
Beginning next construction season, the following two major projects will be launched, in addition to other road and infrastructure projects:
1. 143rd Street at Southwest Highway – Expansion Project Begins
Widening of 143rd Street to five lanes from Southwest Highway to West Avenue is fully funded and anticipated for 2027–2028. Improvements include new signals, an improved railroad crossing, a multi use path, full intersection upgrades and aging watermain replacement. This regional, multi agency project will officially move into construction, advancing long-planned widening and corridor improvements.
2. 153rd Street & Ravinia Avenue – Intersection / Roundabout Improvement
Work begins next year to build a roundabout and upgrade this intersection to cut down delays and keep pedestrians safe.
We will continue providing updates as schedules shift due to weather, permitting, funding and contractor availability. Thank you for your patience as we invest in safer, more reliable roads and infrastructure throughout the Village.