New sidewalks, improved drainage, upgraded signals and more are taking shape across Perrysburg! Here’s your latest look at the progress being made on City projects:
🚧 Downtown Revitalization Project – Phase 2 – Crews poured additional traffic signal pole and pedestrian signal pedestal foundations and continued construction of the block planters. The stone base for the new 10-foot-wide sidewalk was also installed, and two additional drainage inlets were added in the brick paver areas.
Next week: Block planter construction will continue, and the 10-foot-wide sidewalk is scheduled to be poured in the 100 block.
🚧 Fort Meigs Road Ditch Improvement Project – Work continued on the sheet pile cap, including formwork, shear stud installation and rebar placement.
Next week: Crews will continue work on the sheet pile cap, including formwork, shear studs and rebar.
🚧 SR 25 (North Dixie Highway) Multi-Use Path Project – Excavation and stone base installation continued for the new multi-use path. Crews also began saw-cutting concrete driveways in preparation for removal, while AT&T worked on relocating and adjusting utility pedestals and pull boxes.
Next week: Excavation and stone base installation will continue.
🚧 2026 Neighborhood Resurfacing Project – The contractor began saw-cutting areas scheduled for curb and sidewalk replacement. The project will also upgrade existing curb ramps to meet current ADA requirements. Next is the concrete removals and preparation for the new curb, sidewalk and curb ramps will begin in the coming weeks.
🚧 2025 Traffic Signal Improvements – Restoration work continued this week, with crews installing topsoil, seed and straw in areas disturbed during construction.
For the latest City construction updates, visit:
bit.ly/perrysburgprojects