
04/05/2025
Last week’s “Scorpions On The Trail” Work Summary
It was a busy week with three trail work days.
Saturday March 29th and Thursday April 3rd: We had two days at the Cloverpatch Connector trail. On Saturday Sig, Mike S., Alex, Sue and Andy worked on bridge #3. Alex, Sue completed assembling the vertical posts and started assembling the bridge rails starting with the bottom most “curb rail” which is roughly 6-7” in diameter. Andy and Mike continued to build up the on/off bridge ramps with rock and dirt. We also hunted down two additional cedars since it soon became apparent that we were going to be short. By the end of the day we had the curb rail up on the downstream side and three quarters of the way on the upstream side. The bridge is about 21 ft long so we needed a minimum of about 200ft of cedar to build all three rails and the support structure.
On the following Thursday we had a big crew of 9 and split up into a tread crew and a bridge crew. The tread crew (Mike S. Andy, Tom B., and Billy) headed into the trail from the TH further up 5826 where the trail crosses the road. It’s a little shorter hike form there to where they left off last time. They had about 50 more feet of tread to build before they reached the site of “bridge to be #4”. It was a tough 50 ft though as they were on a steep side slope and had to excavate a lot of dirt and rock to build a decent tread bench. Since they were very close to the bridge footing locations they stashed all the rock the excavated for later use when constructing the bridge. By about 1 PM they completed the trail all the way to the near side bridge footing.
The bridge crew, Sig, Peggy, Steve, Alex and Chris, stripped the last 2 cedars of bark and assembled the rest of the rails. By about 1:30PM all the rails were up. The bridge is structurally complete. The on/off bridge ramps need a few more inches of rock and fill but we are going to fold off on that until it dries out a bit. After 13 trail work days, 110 crew members and 772 total crew hours Cloverpatch bridge #3 is complete and the tread has been cut to bridge to be #4. A big thanks to all who contributed to this project! We are going to take a break from Cloverpatch for a while the let things dry .
Friday April 4th - A crew of 7 headed to the South Willamette trail #3645 to logout between Crale Creek Rd and the junction with Eula Ridge and Lawler trail. We had good recent scouting reports for this trail from the jct with Hardesty to Eula so we knew where the work was. Mike S., Andy and Jean headed in from the Eula ridge side with a chainsaw and cleared the 1 plus mile section to Harper Creek of logs and piles of fallen limbs. Sig, Mike K., Dave K. and Garrett armed with two XC saws, axe, wedges, and our Al pry bar, which we all love, to tackle a 1 mile section towards Harper Creek from the Crale Creek side. We entered the trail via and old logging road and a short bushwack to were the logs were. Most of our time was spent most of our time on a large log that crossed the trail twice and was pinned between three trees which provided some interesting lateral binds. We used crosscuts on this section since one of the crew members needed to get recertified. Both crews were done around lunch time. A beautiful day to b e in the forest. The South Willamette trail is now clear from Hardest to the jct with Eula and Lawler.
Hope to see you on the trail soon.
Next week's project: Middle Fork Trail bridge and tread work - Thursday April 10th
Sign up link: https://bttr.im/zqtgc
Other activities:
Scorpion Trail Crew Social Meeting
A party, get together, will be held at the Bob Keefer Center 250 S. 32nd Street, Springfield. The time is from 5:00 to 7:00 Friday April 11th.
Ask for directions at the front desk for the room for the Scorpions. I am having this primarily for long time members to meet and get better acquainted with the newer members. There will be a booklet about Ron Robinson and his written history of the Scorpions for the folks that are not familiar with how it all came about. There will be finger food, water and soft drinks provided as well as delicious cake. I hope to hear from everyone that has not contacted me yet, especially newer members. Spouses are invited as well. Please email me at [email protected]. Thank you and hope to see you then. Jim