Rockland Highway Department

Rockland Highway Department This is the official page of the Rockland Highway Department.

08/22/2026

UPDATE:
Late Summer Summary:

North Ave curb and walk project phase 2:
Have just added binder coat to curb project at the section from Lancaster to Division Street. Will be confirming and signing off on all structure, Gates and curb boxes. Will add topcoat once sign offs are confirmed. We have started to pull the curb on the odd side of North ave and will be installing granite curb the beginning of next week. We will follow up with grading and asphalt binder once all structure and gates have been refurbished and/or replaced. We will continue the process on the even side once we have everything over to binder for pedestrian flow. The approximate completion date will be November.
Funds used: Complete Streets grant, Town Articles, Drainage and Highway General.

Concord Street curb and walk project from 365 Concord Street to Summer Street intersection:
Concord Meadows Development s completed their sidewalk remediation to Shaw Ave. The town will continue curb and walks rehabilitation to Summer Street intersection. The intersection will have new crossings pushed out away from Intersection format. We have stated to pull existing walk and curbing and will continue this week. Once completed the contractor will be in to install new curbing. We will follow up with Structure, curb box, and gate refurbishment. Will then install asphalt binder, confirm infrastructure upgrades and final coats. The intersection will have new crosswalks and additional signage installed.
Funds used: Developer remediation, Chapter 90, Drainage and Highway General.

Manzella Ct and Digrande Drainage project:
We will be starting drainage upgrades to this area. Will include replacing pipe sequencing, manhole rehabilitation, And catch basin rehabilitation. The work is in preparation for paving the roads in Spring 2027.
Funds Used: Chapter 90, and Drainage and Highway General.

Marks and Woodsbury Drainage project: This project will be the same scope as Manzella/Digrande area. Funding sources are the same.

Drainage/Stormwater:
Concord Street from John Dunne Drive to Market is currently being engineered for substantial drainage upgrades. This area will have new easement that runs to Calvery Chapel established drainage easement.
Funds used:
Stormwater/Drainage and Highway General.

Rice Ave from North and South Douglas to Cottonwood is currently being engineered for substantial drainage upgrades. The area will have new easements added, culver with additional and closed elements.
Funds used:
Stormwater/Drainage and Highway General.

Recycle Center Composting operations: We will continue to grind and compost all our organic products. Trying to clean up the area for future operations. Loam, Compost, Mulch and woodchips are available for Town residents.
Funds used: Town Article and Drainage and Highway General.

Highway Department paving:
The Highway Department had Substantial grading, drainage upgrades and asphalt binder installed. Looks great. will be adding topcoat next fiscal year.
Funds used: Town Article, Drainage and Highway General.

Police Station paving project:
We are getting ready to raise the castings and gates to add the topcoat to the police Station. We will also be paving the road from Market Street and the Rail Trail access road. We will be following up with new striping and signage in this area.
Funds used: Town articles, and Highway General.

We are currently finalizing the 5- and 10-year road management plan. All of the Town roads have just been inspected and evaluated on condition. We will be releasing the 5 year plan by the end of year. Obviously will be dependent on grants, Chapter 90 and Town articles.

In addition to the above projects, we will continue on weekly sweeping, drainage maintenance and brush cutbacks.

Thank you for your patience.

07/20/2026

ROAD WORK UPDATE:

AREA: Hingham Street State layout between Burger King and BMW Dealership. The State will start work tonight and the timeline is about 8-10 nights during the weeknights. 8PM-5AM approximately. Tonight (Monday) they will be milling. The rest of week they will be installing traffic loops. We have been told the paving will be done the beginning of next week. Striping will follow the pavement process. This is a MassDOT project. Seek alternate route if possible. There will be delays.

Road work advisory Rt 139 Hanover at Circuit Street detour at intersection. Paving 7-3.  Detouring traffic through Rockl...
06/19/2026

Road work advisory

Rt 139 Hanover at Circuit Street detour at intersection. Paving 7-3. Detouring traffic through Rockland.

North Ave. Rockland. At Division Street area. Excavation work. Caution through work zone.

06/06/2026

UPDATE:

We are Wrapping up Fiscal year 26 and moving onto Fiscal 27.
projects starting:

Concord street curb and walk project phase 1: Concord Meadows remediation project. From 365 Concord to Shaw Ave. The Town will continue after from Shaw Ave to the intersection of Summer Street and will add new ADA compliance crossings.
Funds being used: Developer Remediation, Chapter 90, Drainage and Highway General.

North Ave curb and walk project phase 2: Will continue removal and replacement of all existing curbing and walks. We have started pulling from Lancaster Street to Leisure woods Drive. The project will continue all year until completed.
Funds being used: Complete Streets Grant ($500,000) and multiple Town Articles, Drainage and Highway General.

Drainage/Stormwater: Concord Street from Market to John Dunne Drive drainage rehabilitation and replacement. Currently finishing up engineering. Rice Ave drainage rehabilitation and replacement. Currently finishing up engineering. Both projects will be started this year. Additional drainage work on Marks, Woodsbury, Manzella, Digrande, Topping, Bowen, Harlow and Ellenor. Preparation for road work.

Recycle Center: Will continue with composting and grinding to get us down to zero status. Mulch, woodchips, compost and loam is available to residents. Self-service.

Sweeping: The Street sweeper is back from repairs and we will continue sweeping. We will be giving updates to where the sweeper is going.

We will be giving a more extensive update next week. This is what is currently ongoing. This year is a Gap year as far as road work. We will be concentrating on Maintenance to all roads; drainage refurbishments associated with upcoming road projects as well as extensive patching and crack filling.

Thankyou for your patience

04/03/2026

Sanders are officially coming off today. Goodbye Winter.....You weren't nice this year

Post storm update:Crews are still working on clearing sidewalks and widening roads. With the rain and melting it is impe...
03/06/2026

Post storm update:

Crews are still working on clearing sidewalks and widening roads. With the rain and melting it is imperative to clear catch basins throughout Town. Crews are also removing roadside debris from storm. Next week we will be concentrating on potholes and trees that came down during storm.
Thankyou for your continued patience

Post storm updateWill be removing snow overnight at major intersections throughout Town. 1030-630. Will be at intersecti...
03/02/2026

Post storm update

Will be removing snow overnight at major intersections throughout Town. 1030-630. Will be at intersections 1030-430 and will move over to schools 430-630. Should be last of full overnights.

Thank you for your patience

STORM CLEANUP We will be continuing with post Blizzard cleanup today. Specific areas today and tomorrow are Wyman Fields...
03/02/2026

STORM CLEANUP

We will be continuing with post Blizzard cleanup today. Specific areas today and tomorrow are Wyman Fields, Summit and Exchange areas, as well as Forest Street areas. We will also be continuing on all Main Street walkways. We will then be heading into Millbrook, Frenches Crossing and Winter Circle neighborhoods.

Punxsutawney Phil has been assisting on cleanup due to his lack of canceling Winter…….

Thankyou for your patience.

Snow update: Reminder we will be clearing snow from Center tomorrow from 4am- 12 pm.  4 am crews will be at Vfw intersec...
02/27/2026

Snow update:
Reminder we will be clearing snow from Center tomorrow from 4am- 12 pm.
4 am crews will be at Vfw intersection, North Ave intersection and West/Eastwater intersection. We will then concentrate on center from North Ave to Webster (5-8am)
Webster to West/Eastwater (8-12pm)
Approximate times.
Please seek alternate routes.
Sides will be closed in affected areas.

Thank you for your patience

02/26/2026

Upcoming closures for Friday February 27, 2026. Old Market from 7am till 9am. Union Street from Market Street to West Water/ East Water Street from 9am till 2pm for snow removal. Please use alternate routes. Thank you for your patience.

Address

841 Market Street
Rockland, MA
02370

Opening Hours

Monday 8:30am - 3:30pm
Tuesday 8:30am - 3:30pm
Wednesday 8:30am - 3:30pm
Thursday 8:30am - 3:30pm
Friday 8:30am - 3:30pm

Telephone

(781) 878-0634

Alerts

Be the first to know and let us send you an email when Rockland Highway Department posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Organization

Send a message to Rockland Highway Department:

Shortcuts

Share