City of St. Bonifacius

City of St. Bonifacius Welcome to the official page for the City of St. Bonifacius, MN. Saint Bonifacius is located on MN State Hwy 7 & Cty Rd 92 in Hennepin County.

We are one square mile completely surrounded by the City of Minnetrista. This is the official City of St. Bonifacius' page. It is designed to provide information about the operation of our local government, community news, promotion of local events and answers to many frequently asked questions. While we welcome public participation on our social media page, this page will be moderated an

d the City reserves the right to remove posted content that contains vulgar language, personal attacks of any kind, or offensive comments that target or disparage any ethnic, racial, religious or other group. We also reserve the right to delete spam, posts that advocate illegal activity and posts that infringe on copyright. For more information about the City’s page, contact Ashley Fitzgerald at [email protected] or 952.446.1061

08/25/2026

Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.

Week of August 24th:
Elmwood Neighborhood: The contractor has completed water services on Elmwood Drive. This week they are beginning storm sewer installation on Elmwood Drive and will be completed with that task this week. During this utility work, trenches will be open in the streets, limiting street access during the workday. This week, the street grading crew will begin grading the street subgrade, placing draintile, and adding aggregate for the new roadbed.

Oakwood Road: Removal of driveways and other items will continue this week. The Temporary Water System will be hooked up to houses. Once storm sewer is complete on Elmwood Drive, that crew will move over to begin watermain construction on Oakwood. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Other Project Areas: No anticipated work this week. Removals have been marked in the street in preparation for upcoming work.

Week of August 31st:
Elmwood Neighborhood: Street construction and draintile installation will continue on Elmwood Drive. It is possible that the watermain drilling crew will begin work in the cul-de-sacs of Elmwood Circle and Valleyview.

Oakland Road: Watermain construction will be wrapping up and move into water service construction. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Other Project Areas: Reclamation of the street pavement on Marshland Ct, Meadowview Ter, Wehle Pl, Fire Station, and Highland Driveway are currently anticipated to occur on September 2 and September 3. These dates may change and should anticipate any of the day being possible for this work. Some curb and driveway removals on Marshland, Meadowview Terrace, and Wehle might begin as well. Access will generally remain normal for the most part with some short duration limits during certain activities. No parking will be allowed on the streets during the reclamation days, but residents can park in driveways and garages during that time.

Looking Ahead:
Elmwood Neighborhood: Street construction will continue on Elmwood Drive. Elmwood Circle and Valleyview will see watermain construction following Oakwood utilities. Watermain construction by drilling to the TH 7 watermain connections is possible for early September if it has not been started by the week of August 31.

Oakwood Road: Construction of storm sewer will follow the water utility work. Once all utilities are completed, the street section will be built. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Other Project Areas: Following reclamation of the street pavement, draintile construction is anticipated to possibly begin on Marshland Court and Wehle Pl in spot locations. The streets will remain gravel for a few weeks with limited work besides removing some of the excess aggregate from the reclamation process. Access should be normal for the most part with some short duration limits during certain activities.

08/24/2026
08/19/2026

Week of August 17th:
Elmwood Neighborhood: The contractor has completed the watermain on Elmwood Drive and made the connection to Wildwood Ave. Water services are beginning in the cul-de-sac of Elmwood Drive and working their way towards Wildwood Ave. Towards the end of this week, storm sewer construction could begin. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Oakwood Road: It is likely that later this week the Temporary Water System will be hooked up on Oakwood. Affected properties will receive notices prior to temporary connections.

Other Project Areas: No anticipated work.

Week of August 24th:
Elmwood Neighborhood: Storm sewer construction is anticipated on Elmwood Drive. During this utility work, trenches will be open in the streets, limiting street access during the workday. Following storm sewer on Elmwood Drive, the contractor will begin grading the new street subgrade in preparation for the street section to be constructed.

Oakland Road: Temporary Water System will be connected if not completed yet. Watermain construction is anticipated to begin early in the week. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Other Project Areas: No anticipated work.


Looking Ahead:
Elmwood Neighborhood: Street construction will continue on Elmwood Drive. Elmwood Circle and Valleyview will see watermain construction following Oakwood. Watermain construction by drilling to the TH 7 watermain connections is possible for the week of August 31.

Oakwood Road: Construction of water services would follow the watermain installation.

Other Project Areas: It is currently anticipated that Marshland Court, Meadowview Terrace, Wehle Place, and the Fire Station will have the street pavement reclaimed the week of August 31.

Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Please remain patient as crews work to improve your streets and utilities. We thank you in advance for your cooperation.

08/06/2026

2026 Street and Utility Improvement Project Update

Week of August 3rd:
The contractor has completed connecting the temporary water service system and will now begin working on sanitary sewer on Elmwood Drive at the intersection of Valley View. It is anticipated that the sanitary sewer work will be completed by the end of the week. It is possible that work on the watermain on Elmwood Drive could begin towards the end of this week. This watermain work would begin in the cul-de-sac of Elmwood Drive and work their way towards Elmwood Circle.

Week of August 11th:
Watermain construction is expected to occur on Elmwood Drive, Elmwood Circle and potentially begin on Valley View. During this utility work, trenches will be open in the streets, limiting street access during the workday.

Looking Ahead:
Following watermain construction, the contractor will begin water service construction. This would follow a similar order of starting on Elmwood Drive cul-de-sac and work their way to the east. No work on other neighborhood locations is anticipated until approximately late August at this time.

Schedules are subject to change due to weather, contractor scheduling, and other factors outside the control of the City and Contractor. Your patience is well appreciated as crews work to improve the city streets and utilities.

We thank you in advance for your cooperation.

Tonight at Missile Park from 6-8 pm
08/04/2026

Tonight at Missile Park from 6-8 pm

07/28/2026

Elmwood Residents: temporary mailboxes were installed on Wildwood Avenue. As for garbage service tomorrow: please label the lid of your cans (duct tape) with your house # and place as usual in the street.
Any other questions should be directed to Ben Selinger, the on-site contact. His phone # is (612) 590-6634

07/28/2026

Tornado sirens are being tested today.

07/27/2026

2026 Street & Utility Project Update: work has started on Elmwood Drive today.

THE CITY COUNCIL WILL BE HOLDING A BUDGET WORKSHOP ON AUGUST 26 AT 6:00 PM IN THE COUNCIL CHAMBERS. THE MEETING IS OPEN ...
07/21/2026

THE CITY COUNCIL WILL BE HOLDING A BUDGET WORKSHOP ON AUGUST 26 AT 6:00 PM IN THE COUNCIL CHAMBERS. THE MEETING IS OPEN TO THE PUBLIC.

EUREL NWACHI
ADMIN/CLK/TRS
Posted 7-21-2026

Address

8535 Kennedy Memorial Drive
Saint Bonifacius, MN
55375

Opening Hours

Monday 8am - 4:30pm
Tuesday 8am - 4:30pm
Wednesday 8am - 4:30pm
Thursday 8am - 4:30pm
Friday 8am - 4:30pm

Telephone

+19524461061

Alerts

Be the first to know and let us send you an email when City of St. Bonifacius posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Shortcuts

Share