06/04/2026
DENNIS WASTEWATER PROJECT UPDATE JUNE 4, 2026
RJV Construction Corporation started work in late June 2025 for Contract No. 4. Robert B. Our Company, Inc. started work for Contract No. 2 in early July 2025. Dig It Construction LLC started work for Contract No. 3 in mid- July 2025. Work is currently scheduled as outlined below.
Work for the week of June 8 – June 12:
Contract No. 2:
• Continued sewer work on Main Street, two work zones: Highbank Road to approximately 550 feet south and from Cape Cod Rail Trail to Highbank Road. HIGHBANK/MAIN INTERSECTION WORK IS COMPLETE AND ACCESS IS OPEN ALONG HIGHBANK ROAD BUT CLOSURES REMAIN FOR MAIN STREET IN BOTH THE NORTH AND SOUTH DIRECTIONS. Continued sewer work on Theophilus F. Smith Road, east from Route 134 - ACCESS TO TRANSFER STATION WILL BE RESTRICTED TO SOUTH GAGES WAY ON WEDNESDAY THROUGH FRIDAY. Police detail(s) will be on-site and signage in place to assist residents. Some road closures with local traffic only, detours will be in place.
Contract No. 3:
• Continued sewer work on Baxter Street from Route 28 to Center Street. Local traffic only, detour will be in place. Police detail(s) will be on-site and signage in place to assist residents.
Contract No. 4:
• No scheduled work.
Two Week Look Ahead (6/15 – 6/19):
Contract No. 2:
• Continued sewer work on Main Street, two work zones: Highbank Road to approximately 550 feet south and from Cape Cod Rail Trail to Highbank Road. HIGHBANK/MAIN INTERSECTION WORK IS COMPLETE AND ACCESS IS OPEN ALONG HIGHBANK ROAD BUT CLOSURES REMAIN FOR MAIN STREET IN BOTH THE NORTH AND SOUTH DIRECTIONS. Continued sewer work on Theophilus F. Smith Road, east from Route 134 - ACCESS TO TRANSFER STATION WILL BE RESTRICTED TO SOUTH GAGES WAY ON WEDNESDAY THROUGH FRIDAY. Police detail(s) will be on-site and signage in place to assist residents. Some road closures with local traffic only, detours will be in place.
Contract No. 3:
• Continued sewer work on Baxter Street from Route 28 to Center Street. Local traffic only, detour will be in place. Police detail(s) will be on-site and signage in place to assist residents.
Contract No. 4:
• No scheduled work.
Three Week Look Ahead (6/22 – 6/26):
Contract No. 2:
• Completion of sewer work on Main Street, two work zones: Highbank Road to approximately 550 feet south and from Cape Cod Rail Trail to Highbank Road. HIGHBANK/MAIN INTERSECTION WORK IS COMPLETE AND ACCESS IS OPEN ALONG HIGHBANK ROAD BUT CLOSURES REMAIN FOR MAIN STREET IN BOTH THE NORTH AND SOUTH DIRECTIONS. Completion of sewer work on Theophilus F. Smith Road, east from Route 134 - ACCESS TO TRANSFER STATION WILL BE RESTRICTED TO SOUTH GAGES WAY ON WEDNESDAY THROUGH FRIDAY. Police detail(s) will be on-site and signage in place to assist residents. Some road closures with local traffic only, detours will be in place.
Contract No. 3:
• Continued sewer work on Baxter Street from Route 28 to Center Street. Local traffic only, detour will be in place. Police detail(s) will be on-site and signage in place to assist residents.
Contract No. 4:
• No scheduled work.
ADDITIONAL WORK
Work has started on the future recharge Site 2 located at the Corner of Old Bass River Road and Bob Crowell Road. The Town’s Comprehensive Wastewater Management Plan cites requirements for a second site for recharge of treated effluent from the new Water Resource Recovery Facility (WRRF) located on Theophilus Smith Road. Recharge for current Phase 1 work will occur at the WRRF site. However, due to DEP permitting limitations it will be necessary to also recharge at Site 2 during Phase 1. Site clearing is currently on-going at this location to determine future design requirements.
Please note that this is a projected schedule and will be adjusted accordingly based on the Contractors’ actual progress and the weather.
Roads will be passable at the end of each day. Police Details and Contractors will work with residents and businesses to ensure their needs for access are addressed.
Police Details and signage will be in-place to assist motorists in reaching their destination.
Normal work hours are 7:00 AM to 4:00 PM Monday to Friday, weather permitting, unless otherwise noted.
Wastewater Project Updates are being posted to the Town’s website at http://www.town.dennis.ma.us under “NEWS & ANNOUNCEMENTS” where you can also sign up for email notifications of updates. We encourage you to visit the Wastewater page link https://www.town.dennis.ma.us/356/Wastewater for additional information regarding the Wastewater Program.
Thank you for your patience and cooperation during this important project to restore and protect our environment.