🚧 ROAD WORK UPDATE 🚧 For the week of 9/14/26, Monday–Friday, 7 a.m.–5 p.m.
Please consider sharing this post and information with your friends and family who may not follow our page but travel our roads.
If you have any questions or concerns regarding the Wastewater Project, please contact Ryan Chase, Assistant Wastewater Superintendent, at 508-771-7921.
Learn more about the project by visiting https://www.yarmouth.ma.us/.../Wastewater-Construction...
To learn more information about the Route 6A road work, visit https://www.yarmouth.ma.us/2329/Route-6A-Water-Main-Project
Monday September 14th – Friday September 18th
Sewer preparations on Route 28 near Parker’s River Landing
· The sewer contractor will continue installation of dewatering wells on Route 28 between Courtland Lane and Parker’s River.
· One lane alternating traffic will be maintained.
Water Main work on Route 6A
· Water main installation on Route 6A between Railroad Avenue and Wharf Lane.
· One lane alternating traffic will be maintained.
Bass River Bridge Project
· Drainage work on North Main Street and Old Main Street.
· One lane alternating traffic will be maintained.