08/31/2026
It’s the 5th Monday of the month, which means no regularly scheduled Planning Commission or BOMA meeting. An empty day on the calendar makes for a good opportunity to share updates across a wide range of projects and activities.
- Reserve Blvd and Kedron Rd signalization; Installation work should begin in the coming weeks.
- Cleburn Rd and Beechcroft Rd signalization and turn lanes; TDOT has approved plans. City completing last required steps to be able to go to bid, select contractor and begin work.
- Mahlon Moore Rd and Battle Creek Way improvements; work is substantially complete.
- Buckner Lane widening; construction on last segment scheduled to be complete this calendar year.
- Kedron Rd and Old Kedron Rd improvements; City has acquired ROW. Project expected to be completed in house.
- Port Royal Rd and Buckner Ln improvements; project ready for bid. Expected to begin work in coming months.
- I-65 improvements between Saturn Parkway and I-840; TDOT expected to issue design build award in Q3 2027 with construction work to begin in 2028. https://www.tn.gov/tdot/projects/region-3/interstate-65-widening-near-june-lake.html
- I-65 Improvements between Thompsons Lane and Bear Creek Pike; PEL study underway with TDOT, expected to be complete in Q1 2027. No current public timeline for when additional pre-construction steps may occur.
- Hwy 31 widening; preliminary design work underway, with TDOT projecting right-of-way acquisition work to occur in FY28. https://www.tn.gov/tdot/projects/region-3/state-route-6.html
- Jim Warren bridge replacement; funded by private development, construction activity expected to begin in early 2027.
- Community Services Annex; City continues site preparation work with in house team. This project must be completed to relocate the public works department to allow for the water reclamation plant expansion.
- Harvey Park new playground equipment; being installed now. Should be completed soon.
- Sewer force main to Columbia; Spring Hill is negotiating an interlocal agreement with the City of Columbia. Once the agreement is complete, expect a 21-24 month build timeline.
- Pure Water Spring Hill reservoir; geotechnical work underway.
- Pure Water Spring Hill design build package; BOMA is expected to consider a design build agreement in September. This would be the major package that needs to be complete prior to the moratorium ending.
- Southside water tank; construction complete. Will come on line this fall.
- Sam’s Club; expected to begin vertical construction soon.
- Medacta; road improvements already underway. Site work expected to begin in September with vertical construction beginning Q1 2027.
- June Lake commercial; site work underway for previously approved salon, credit union and multitenant buildings. Additional commercial projects will be able to move forward as additional sewer capacity becomes available.
- Kedron Square; no sewer allocation under the moratorium means its unlikely anything occurs prior to additional capacity becoming available.
- Other Legacy Pointe commercial; nothing to announce now. Additional commercial projects will be able to move forward as additional sewer capacity becomes available.
- Comprehensive Plan update; City awarded an agreement in August. Kick off meetings being scheduled.
- Parks Master Plan update; BOMA scheduled to vote on a potential agreement in September. Project has come in over budget.
- Maury County EMS coverage; Williamson and Maury county continue to work together to find a solution for a single provider to service all of Spring Hill beginning Jan 1, 2027.
Most of these items and others were also covered during the state of the City address back at the beginning of August. If you missed that presentation, you can see it here: https://play.champds.com/springhilltn/event/1234
Did I miss something you’re interested in? Drop a question in the comments.